Mich. Admin. Code R. 460.1006 - Distributed generation program application and fees
Rule 106.
(1) An
electric utility or alternative electric supplier may use an online distributed
generation program application process. An electric utility or alternative
electric supplier not using an online application process may utilize a uniform
distributed generation program application form that must be approved by the
commission. An electric utility's distributed generation program application
may be combined with an electric utility's interconnection
application.
(2) A customer taking
retail electric service from an electric utility and applying to participate in
the distributed generation program shall concurrently submit a completed
distributed generation program application and interconnection application or
indicate on the distributed generation program application the date that the
customer applied for interconnection with the electric utility and, if
applicable, the date the customer received authorization to operate in parallel
pursuant to R 460.968. All of the following
requirements apply:
(a) When a distributed
generation program application is accompanied by an associated interconnection
application, an electric utility may complete its review of the distributed
generation program application before, during, or after processing the
interconnection application pursuant to part 2 of these rules,
R 460.911 to
R 460.992. Both of the following
requirements apply:
(i) Combined with the
notification of interconnection application completeness and conformance
pursuant to R 460.936, an electric utility shall
notify the customer whether the distributed generation program application is
accepted, and provide an opportunity for the customer to remedy any application
deficiencies pursuant to the timelines in
R 460.936(7)(b) or
withdraw the application. If the customer fails to remedy the application
deficiencies within the timelines in
R 460.936(7)(b), the
electric utility may consider the distributed generation program application
withdrawn without refund of the application fees.
(ii) While processing the interconnection
application, which may include, but is not limited to,
R 460.946 fast track initial review,
the electric utility shall determine whether the appropriate meter is installed
for the distributed generation program.
(b) If a distributed generation program
application is filed with an already in-progress interconnection application,
the electric utility may process the distributed generation program application
in parallel with the interconnection application pursuant to part 2 of these
rules, R 460.911 to
R 460.992, subdivision (2) of this
subrule, if practicable, or adopt the review process pursuant to subdivision
(c) of this subrule.
(c) If a
distributed generation program application is filed with an in-progress
interconnection application and the electric utility determines it is not
practicable to process the distributed generation program application in
parallel with the interconnection application or the distributed generation
application is filed subsequent to the customer receiving authorization to
operate its eligible generator in parallel pursuant to
R 460.968, the electric utility shall
process the distributed generation program application pursuant to all of the
following:
(i) The electric utility has 10
business days to review the distributed generation program application and
determine whether to accept the application pursuant to the timelines in
R 460.936(6) and
(7). The timelines in
R 460.936(7)(a)
apply to utility notifications. The electric utility shall provide the customer
an opportunity to remedy any application deficiencies pursuant to
R 460.936(7)(b). If
the customer fails to remedy the application deficiencies within the timelines
in R 460.936(7)(b), the
electric utility may consider the distributed generation program application
withdrawn without refund of the application fees.
(ii) Within 10 business days of providing
notification to the customer that the distributed generation program
application has been accepted, the electric utility shall determine whether the
appropriate meter, or meters, is installed for the distributed generation
program.
(d) If a
customer approved for participation in the distributed generation program
requires a new or additional meter or meters, the electric utility shall
arrange with the customer to install the meter or meters at a mutually agreed
upon time.
(e) The electric utility
shall complete changes to the customer's account to permit distributed
generation program credit to be applied to the account no more than 10 business
days after the necessary meter is installed and all necessary steps in
R 460.966 are
completed.
(3) A customer
taking retail electric service from an alternative electric supplier shall
submit a completed distributed generation program application to the
alternative electric supplier and provide a copy to the electric utility that
provides distribution service. All of the following requirements apply:
(a) The alternative electric supplier shall
process the distributed generation program application according to the
applicable timelines in subrule (2)(a) through (d) of this rule.
(b) The electric utility shall notify the
alternative electric supplier when it has provided the applicant authorization
to operate the eligible electric generator in parallel pursuant to
R 460.968 and, if applicable, that
installation of the appropriate meter or meters is completed.
(c) Within 10 business days of the electric
utility's notification, the alternative electric supplier shall complete
changes to the applicant's account to permit distributed generation program
credit to be applied to the account.
(4) If a distributed generation program
application is not approved by the alternative electric supplier, the
alternative electric supplier shall notify the customer and the electric
utility of the reasons for the disapproval. The alternative electric supplier
shall provide the customer an opportunity to remedy the deficiency pursuant to
the timelines in R
460.936(7)(b) or withdraw the
application. If the customer fails to remedy the application deficiencies
within the timelines in
R 460.936(7)(b), the
alternative electric supplier and electric utility may consider the distributed
generation program application withdrawn without refund of the application
fees.
(5) If a customer's
distributed generation program application is approved, the customer shall have
a completed and approved installation within 6 months from the date the
customer's application is considered complete, or the electric utility or
alternative electric supplier may consider the application withdrawn without
refund and shall have no further responsibility with respect to the
application.
(6) The distributed
generation program application fee for electric utilities and alternative
electric suppliers shall not exceed $50. The electric utility shall specify the
fee on the electric utility's distributed generation program tariff sheet or in
the alternative electric supplier's distributed generation program
plan.
(7) The customer shall pay all
interconnection costs pursuant to part 2 of these rules,
R 460.911 to
R 460.992, which include all electric
utility costs associated with the customer's interconnection that are not a
distributed generation program application fee, excluding meter costs as
described in R 460.1012 and
R 460.1014.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.