Mich. Admin. Code R. 460.901a - Definitions; A-I
Rule 1a. As used in these rules:
(a) "AC" means alternating current at 60
Hertz.
(b) "Affected system" means
another electric utility's distribution system, a municipal electric utility's
distribution system, the transmission system, or transmission system- connected
generation which may be affected by the proposed interconnection.
(c) "Affiliate" means that term as defined in
R
460.10102(1)(a).
(d) "Alternative electric supplier" means
that term as defined in section 10 g of 1939 PA 3, MCL
460.10g.
(e) "Alternative electric supplier
distributed generation program plan" means a document supplied by an
alternative electric supplier that provides detailed information to an
applicant about the alternative electric supplier's distributed generation
program.
(f) "Alternative electric
supplier legacy net metering program plan" means a document supplied by an
alternative electric supplier that provides detailed information to an
applicant about the alternative electric supplier's legacy net metering
program.
(g) "Applicant" means the
person or entity submitting an interconnection application, a legacy net
metering program application, or a distributed generation program application.
An applicant is not required to be an existing customer of an electric utility.
An electric utility is considered an applicant when it submits an
interconnection application for a DER that is not a temporary DER or a
substation backup energy storage device.
(h) "Application" means an interconnection
application, a legacy net metering program application, or a distributed
generation program application.
(i)
"Area network" means a location on the distribution system served by multiple
transformers interconnected in an electrical network circuit.
(j) "Business day" means Monday through
Friday, starting at 12:00:00 a.m. and ending at 11:59:59 p.m., excluding
electric utility holidays and any day where electric service is interrupted for
10% or more of an electric utility's customers.
(k) "Calendar day" means every day, including
Saturdays, Sundays, and holidays.
(l) "Certified" means an inverter-based
system has met acceptable safety and reliability standards by a nationally
recognized testing laboratory in conformance with IEEE 1547.1-2020 and the UL
1741 September 28, 2021 edition except that prior to commercial availability,
inverter-based systems which conform to the UL 1741SA September 7, 2016 edition
are acceptable.
(m) "Commission"
means the Michigan public service commission.
(n) "Commissioning test" means the test and
verification procedure that is performed on a device or combination of devices
forming a system to confirm that the device or system, as designed, delivered,
and installed, meets the interconnection and interoperability requirements of
IEEE 1547-2018 and IEEE 1547.1-2020. A commissioning test must include visual
inspections and may include, as applicable, an operability and functional
performance test and functional tests to verify interoperability of a
combination of devices forming a system.
(o) "Conforming" means the information in an
interconnection application is consistent with the general principles of
distribution system operation and DER characteristics.
(p) "Customer" means a person or entity who
receives electric service from an electric utility's distribution system or a
person who participates in a legacy net metering or distributed generation
program through an alternative electric supplier or electric utility.
(q) "DC" means "direct current."
(r) "Distributed energy resource" or "DER"
means a source of electric power and its associated facilities that is
connected to a distribution system. DER includes both generators and energy
storage devices capable of exporting active power to a distribution
system.
(s) "Distributed generation
program" means the distributed generation program approved by the commission
and included in an electric utility's tariff pursuant to section 6a(14) of 1939
PA 3, MCL
460.6a, or established in an
alternative electric supplier distributed generation program plan.
(t) "Distribution system" means the
structures, equipment, and facilities owned and operated by an electric utility
to deliver electricity to end users, not including transmission and generation
facilities that are subject to the jurisdiction of the federal energy
regulatory commission.
(u)
"Distribution upgrades" mean the additions, modifications, or improvements to
the distribution system necessary to accommodate a DER's connection to the
distribution system.
(v) Electric
utility" means any person or entity whose rates are regulated by the commission
for selling electricity to retail customers in this state. For purposes of
R 460.901a through
R 460.992 only, "electric utility"
includes cooperative electric utilities that are member regulated as provided
in section 4 of the electric cooperative member-regulation act, 2008 PA 167,
MCL 460.34.
(w) "Electrically coincident" means that 2 or
more proposed DERs associated with pending interconnection applications have
operating characteristics and nameplate capacities which require that
distribution upgrades will be necessary if the DERs are installed in electrical
proximity with each other on a distribution system.
(x) "Electrically remote" means a proposed
DER is not electrically coincident with a DER that is associated with a pending
interconnection application.
(y)
"Eligible electric generator" means a methane digester or renewable energy
system with a generation capacity limited to a customer's electric need and
that does not exceed either of the following:
(i) 150 kWac of aggregate generation at a
single site for a renewable energy system.
(ii) 550 kWac of aggregate generation at a
single site for a methane digester.
(z) "Energy storage device" means a device
that captures energy produced at one time, stores that energy for a period of
time, and delivers that energy as electricity for use at a future time. For
purposes of these rules, an energy storage device may be considered a
DER.
(aa) "Export capacity" means
the amount of power that can be transferred from the DER to the distribution
system. Export capacity is either the nameplate rating or a lower amount if
limited using an acceptable means that is defined in an electric utility's
interconnection procedures.
(bb)
"Facilities study" means a study to specify and estimate the cost of the
equipment, engineering, procurement, and construction work if distribution
upgrades or interconnection facilities are required.
(cc) "Fast track" means the procedure used
for evaluating a proposed interconnection that makes use of screening
processes, as described in
R 460.944 to
R 460.950.
(dd) "Force majeure event" means an act of
God; labor disturbance; act of the public enemy; war; insurrection; riot; fire,
storm, or flood; explosion, breakage, or accident to machinery or equipment; an
emergency order, regulation or restriction imposed by governmental, military,
or lawfully established civilian authorities; or another cause beyond a party's
control. A force majeure event does not include an act of negligence or
intentional wrongdoing.
(ee) "Full
retail rate" means the power supply and distribution components of the cost of
electric service. Full retail rate does not include a system access charge,
service charge, or other charge that is assessed on a per meter, premise, or
customer basis.
(ff) "Good standing"
means an applicant has paid in full all undisputed bills rendered by the
interconnecting electric utility and any alternative electric supplier in a
timely manner and none of these bills are in arrears.
(gg) "Governmental authority" means any
federal, state, local, or other governmental regulatory or administrative
agency, court, commission, department, board, or other governmental
subdivision, legislature, rulemaking board, tribunal, or other governmental
authority having jurisdiction over the parties, their respective facilities, or
the respective services they provide, and exercising or entitled to exercise
any administrative, executive, police, or taxing authority or power; provided,
however, that this term does not include the applicant, interconnection
customer, electric utility, or any affiliate thereof.
(hh) "GPS" means global positioning
system.
(ii) "Grid network" means a
configuration of a distribution system or an area of a distribution system in
which each customer is supplied electric energy at the secondary voltage by
more than 1 transformer.
(jj) "High
voltage distribution" means those parts of a distribution system that operate
within a voltage range specified in the electric utility's interconnection
procedures. For purposes of these rules, the term 'subtransmission" means the
same as high voltage distribution.
(kk) "IEEE" means institute of electrical and
electronics engineers.
(ll) "IEEE
1547-2018" means "IEEE Standard for Interconnection and Interoperability of
Distributed Energy Resources with Associated Electric Power Systems
Interfaces," as adopted by reference in
R 460.902.
(mm) "IEEE 1547.1-2020" means IEEE 'standard
Conformance Test Procedures for Equipment Interconnecting Distributed Energy
Resources with Electric Power Systems and Associated Interfaces," as adopted by
reference in R
460.902.
(nn) "Inadvertent export" means unscheduled
export of active power from a DER, exceeding a specified magnitude and for a
limited duration, due to fluctuations in load-following behavior.
(oo) "Independent system operator" means an
independent, federally-regulated entity established to coordinate regional
transmission in a non-discriminatory manner and to ensure the safety and
reliability of the transmission and distribution systems.
(pp) "Initial review" means the fast track
initial review screens described in
R 460.946.
(qq) "Interconnection" means the process
undertaken by an electric utility to construct the electrical facilities
necessary to connect a DER with a distribution system so that parallel
operation can occur.
(rr)
"Interconnection agreement" means an agreement containing the terms and
conditions governing the electrical interconnection between the electric
utility and the applicant or interconnection customer. Where construction of
interconnection facilities or distribution upgrades are necessary, the
agreement, or amendments, shall specify estimated timelines, cost estimates,
and payment milestones for construction of facilities and distribution upgrades
to interconnect a DER into the distribution system, and shall identify design,
controls, settings, procurement, installation, and construction requirements
associated with installation of the DER. Standard level 1, 2, and 3
interconnection agreements and level 4 and 5 interconnection agreements are
types of interconnection agreements.
(ss) "Interconnection coordinator" means a
person or persons designated by the electric utility who shall serve as the
point of contact from which general information on the application process and
on the affected system or systems can be obtained through informal request by
the applicant or interconnection customer.
(tt) "Interconnection customer" means the
person or entity, which may include the electric utility, responsible for
ensuring a DER is operated and maintained in compliance with all local, state,
and federal laws, as well as with all rules, standards, and interconnection
procedures. An electric utility is not considered an interconnection customer
for temporary DER or a substation backup energy storage device
project.
(uu) "Interconnection
facilities" mean any equipment required for the sole purpose of connecting a
DER with a distribution system.
(vv)
"Interconnection procedures" mean the requirements that govern project
interconnection adopted by each electric utility and approved by the
commission.
(ww) "Interconnection
study agreement" means an agreement between an applicant and an electric
utility for the electric utility to study a proposed DER.