N.M. Code R. § 17.9.568.25 - GENERAL PROVISIONS APPLICABLE TO INTERCONNECTION CUSTOMERS
A. An
interconnection customer is responsible for the prudent maintenance and upkeep
of its interconnection equipment.
B. Upon the petition of a utility , for good
cause shown, the commission may require a customer with a generating facility
with a rated capacity of 250 kW or less to obtain general liability insurance
prior to connecting with a public utility. A utility may require that an
applicant proposing to connect a generating facility with a rated capacity
greater than 250 kW provide proof of insurance with reasonable limits not to
exceed $1,000,000.00 or other reasonable evidence of financial
responsibility.