N.M. Admin. Code § 17.11.10.31 - BROADBAND PROGRAM
A. It
is the goal of the commission that New Mexico consumers have access to
high-quality broadband service from both wireline and mobile broadband
providers. Pursuant to Subsection N of Section
63-9H-6, NMSA 1978, ETCs may
separately apply to the commission for grants to fund the construction and
maintenance of facilities that are capable of providing broadband internet
access service to areas unserved or underserved by broadband in the state.
Applications must be primarily for coverage of the construction costs of new
facilities, but such applications may include a request for maintenance costs
of those facilities as well. Each grant that is awarded will provide up to
seventy five percent of the budgeted project cost, with the ETC applying the
remainder from its own funds. Projects receiving any source of third-party
funding other than potential loan funds, FCC high-cost fund legacy support or
connect America fund support (including mobility fund support) will not be
eligible. Each applicant shall provide a detailed description in their
application of the origin and type of funding provided for the carrier match,
and a certification that those monies are not duplicative of other purposes or
projects other than SRUSF broadband program projects. In evaluating
applications, the commission shall seek to avoid duplication of service using
the same technology. Awards of support under this section shall be consistent
with federal universal service support programs and be based on the best use of
the fund for rural areas of the state. For purposes of administering the
broadband program, the commission may find that a broadband program proposed
project area is a rural area, notwithstanding the definition of rural area in
Subsection U of
17.11.10.7 NMAC, if it determines
that:
(1) the area otherwise has the
characteristics of a rural area;
(2) the area is unserved or underserved by
broadband; and
(3) the public
interest requires that the area be classified as rural.
B. Funding of the broadband program. At least
eight million dollars ($8,000,000.00) of the fund shall be dedicated annually
to the broadband program. The amount of funding allocated to the broadband
program shall not be subject to proration under Subsection E of
17.11.10.20 NMAC. To the extent a
year's broadband program funding is not exhausted by grants awarded during that
year, the funds will rollover to the following year.
C. Applicants for broadband program grants
may request that company-specific information contained within an application
be treated as confidential. The commission shall make all decisions regarding
disclosure of company-specific information and may request further information
or justification from the contributing company to ensure uniformity of
confidential treatment of all information submitted by contributing companies.
Nothing in this rule shall preclude commission issuance of an umbrella
protective order identifying what reported data shall be, or shall not be,
deemed confidential. The commission staff or a third-party contractor, shall
keep confidential all company-specific information obtained from applicants for
broadband program grants for which confidential treatment is requested, shall
not use such information except for purposes of analyzing the applications, and
shall not disclose such information in company-specific form unless directed to
do so by the commission.
D. Minimum
requirements for eligible projects. The commission will consider projects on a
technology-neutral basis. Projects that apply technologies including, without
limitation, wireline, mobile wireless, and fixed wireless technologies are all
eligible for broadband fund grants. A project must meet the following
requirements to be eligible for a grant award:
(1) support broadband internet access service
at speeds of at least 25.0 Mbps download/3.0 Mbps upload to all households and
businesses in the proposed project area;
(2) support voice grade telephony service to
all households and businesses in the proposed project area. For this purpose, a
voice over internet protocol (VOIP) based service is acceptable, as well as
traditional voice telephony services and mobile voice services;
(3) support access to emergency 911 services;
and
(4) offer a latency that is
sufficiently low to support real-time, interactive applications.
E. Contents of grant applications.
An application for support from the broadband program shall include, at a
minimum:
(1) a proposal to build
telecommunications network facilities to service an area where the applicant is
designated as a state ETC;
(2) a
detailed build plan setting forth a description of the facilities to be
deployed, including all costs of constructing facilities;
and
(3) a
map showing where service and coverage will be provided. This requirement can
be met by providing;
(a) for a wireline
network, a map showing all homes, businesses, and other end user locations
passed; or
(b) for a wireless
network, a coverage map generated using a radio frequency propagation tool
generally used in the wireless industry;
(4) an estimate of the number of road miles
and square miles to be covered and population and population density of the
area covered;
(5) the amount of
support requested from the broadband program and the amount of the applicant's
financial match, and a description of any type, amount, and purpose of subsidy
or financial support the applicant is currently receiving or is scheduled to
receive in the area designated in the application;
(6) a description of the technology to be
deployed, including data throughput speeds and latency characteristics of the
service to be delivered to customers;
(7) a demonstration that the area to be
served is an area unserved by broadband or an area underserved by broadband as
defined in
17.11.10.7 NMAC. If the area to be
served contains served, unserved and underserved areas, the application and map
shall identify which portions of the area are served, unserved and which are
underserved. Each served, unserved, and underserved area shall be clearly
identified through color coding on the map submitted with the application. Each
served, unserved, and underserved area shall be clearly identified through
individual color coding indicators on all city street grid maps submitted with
the applications. Satellite views are not acceptable for the application's
requirement for mapping;
(8) a
demonstration of the estimated customer subscription rates and revenues from
the services to be offered as a result of the proposed construction sufficient
to justify support from the broadband program;
(9) a commitment to provide a minimum
twenty-five percent match of funds;
(10) if the project is a wireless network
deployment, a commitment to allow collocation on reasonable terms by other
providers of commercial mobile wireless service or any public safety network
and to abide by the FCC's collocation requirements for awardees under the
federal universal service program;
(11) sample terms and conditions for the
service and proposed prices;
(12)
explain how the proposed deployment will contribute to the enhancement of
digital equity and digital inclusion in the proposed service
territory;
(13) explain how the
awards of support are consistent with federal universal service support
programs;
(14) a certification by
an authorized representative affirming that all information set forth in the
application is true and correct;
(15) any other requirements to ensure
accountability as the commission may develop and approve in a proceeding to
determine the form and contents of grant applications; and
(16) applications and mapping information
must also be submitted contemporaneously with the New Mexico department of
information technology broadband division.
F. The ETC must make the following
commitments and include them in its application:
(1) the broadband service must be offered at
reasonably comparable rates for comparable services in urban areas;
(2) the broadband service must be provided
for at least seven years following project completion;
(3) the ETC must abide by commission
reporting requirements sufficient to monitor the progress of the project
deployment and to ensure that all grant funds are being used efficiently and
for the purpose intended; and
(4)
the ETC must commit to respond to commission inquiries regarding
service-related complaints and commit to attempt to resolve service-related
complaints in a reasonable manner.
G. Procedure for awarding support from the
fund:
(1) On or before May 1 of each year, the
commission shall open a non-adjudicative, administrative docket and establish a
deadline for filing applications for broadband program support for the
following calendar year. The telecom bureau, or a third-party contractor, shall
review and summarize all timely applications. Only carriers holding ETC status
as of October 1 shall be eligible to receive disbursements from the fund during
the year that begins the following January 1.
(2) Interested persons may seek intervention
in these proceedings, pursuant to
1.2.2.23 NMAC.
(3) On or before September 1, the telecom
bureau shall make a presentation to the commission, with analysis of the
applications for awards. The telecom bureau, or a third-party contractor, may
communicate with applicants to request additional information or clarify
information presented in the applications in order to prepare its presentation.
Such presentations shall be considered by the commission but shall not bind the
commission.
(4) At the September 1
presentation, the telecom bureau shall present a summary of projects. The
telecom bureau shall provide the following information for each project on a
single spreadsheet.
(a) cost per customer
served or passed;
(b) type of
technology;
(c) whether area is
unserved or underserved (or, if area includes both, in what
proportions);
(d) download and
upload speed of service;
(e)
monthly rates that the grantee intends to charge for the service; and
(f) telecom bureau comments on the
project.
(5) On or before
October 15, the commission, in coordination with the broadband office and the
council, for prioritization and alignment with the statewide broadband plan,
shall issue a decision approving or denying in whole or in part, each
application. Among the factors that the commission will consider when selecting
proposed projects for funding are the download and upload speeds that a project
will provide and whether the project will serve an area unserved by broadband
or an area underserved by broadband.
(6) On or before November 1, any interested
person may file with the commission a request for reconsideration, in whole or
in part, of any award of funds. Requests for reconsideration will not be valid
after November 1.
(7) On or before
December 1, the commission shall dispose of any motions for
reconsideration.
H.
Conditions for disbursement of awarded funds:
(1) The awardee commits to complete
construction of its project within three years from the date of the
commission's final order approving an award pursuant to
17.11.10.31 NMAC.
(2) For each awarded project, project reports
shall be submitted to staff, consultant(s), and administrator(s) semiannually,
during June and December and at the mid-point and completion of the project
that provide information regarding the status of the project in a form accepted
by staff. Semi-annual reports shall be submitted June 30, and December 31 of
the calendar year. The midpoint disbursement report shall describe ETC progress
on project milestones at the mid-point of the completion of the project
pursuant to Paragraph (1) of Subsection E of
17.11.10.25 NMAC, prior to the
release of a mid-point disbursement. The mid-point and final reports may be
filed concurrently with the submission of the semi-annual reports, but may not
be combined into one report. Within 30 days after project completion, the
awardee shall submit a final report in a form accepted by staff demonstrating
that the project as completed meets the coverage requirements set forth in the
application, including a certification from an officer or director that all
program requirements have been met.
(3) Prior to the initial disbursement, the
ETC must notify the commission in writing that it is prepared to commence the
project with regard to project engineering, ordering or delivery of required
equipment, labor requirements, and that all permits have been granted to begin
construction. The administrator shall disburse one third of the award promptly
following receipt of the ETC's written notice that it is prepared to commence
the project, one third at the midpoint of the project, and the remaining third
upon project completion. The second and third payments may be requested as a
single disbursement upon completion and are contingent upon the submission of
acceptable project status reports pursuant to Paragraph (2) of Subsection H of
17.11.10.31 NMAC. The commission
may, within 30 days after submission of a report, order additional information
to be provided, suspend payment by the administrator, or take other action as
necessary after notice and hearing.
(4) Any applicant found to have willfully
misrepresented information in an application, is found to have used support
unlawfully, or fails to meet the commitments set forth in the application, may
be subject to refund of award funds or other actions of the
commission.
Notes