N.M. Admin. Code § 17.9.569.8 - GENERAL PROVISIONS FOR INTERCONNECTION APPLICATIONS FOR FACILITES WITH RATED CAPACITIES GREATER THAN 10 MW
A. A utility shall interconnect with any
interconnection customer that:
(1) is in its
service area;
(2) qualifies for the
interconnection procedures in this rule 17.9.569 NMAC;
(3) files an interconnection application in
accordance with Subsection B of
17.9.569.8 NMAC;
(4) meets the utility's system safety
standards;
(5) has paid the
estimated costs of interconnection (if applicable);
(6) has entered into a contract with the
utility pursuant to 17.9.569 NMAC;
(7) has substantially completed a generating
facility that is capable of operating safely and commencing the delivery of
power into the utility system; and
(8) has provided a statement from a licensed
professional electrical engineer certifying that the design of the generating
facility and its interconnection equipment comply with utility requirements and
with reasonable interconnection safety and design standards and prudent
electrical practices.
B.
An interconnection customer subject to this rule 17.9.569 NMAC shall make its
application for interconnection to a utility using the interconnection
application form provided in the interconnection manual and its exhibits,
incorporated by reference in 17.9.568 NMAC.
C. Unless a longer period of time is agreed
to in writing by the interconnection customer, within 30 business days of
receipt of an interconnection application on the prescribed form, a utility
shall furnish to the interconnection customer a good faith, detailed list of
required interconnection equipment and an itemized estimate of the costs that
the proposed interconnection customer will have to pay to the utility to
complete the interconnection. The list of required interconnection equipment
shall not change substantially other than in response to changes in design,
location of equipment, and/or intended operation of the equipment of the
generating facility.
D. If an
interconnection application fails to comply with the requirements of this rule
17.9.569 NMAC or is otherwise insufficient, the utility shall attempt to obtain
the required information to complete the interconnection application by
telephone. If the utility cannot so obtain complete information, the utility
shall within 15 business days of receipt of the interconnection application
notify the interconnection customer specifying the deficiencies in the
interconnection application.
E. If
the interconnection customer disagrees with the utility's determination that
the interconnection application is insufficient, it may within 15 business days
of its receipt of the utility's notification initiate a proceeding before the
commission pursuant to the complaint process of 17.9.570 NMAC. In such a
proceeding, the utility shall have the burden to establish that the rejection
was justified.
F. The
interconnection customer shall give the utility at least 60 days written
advance notice to interconnect. Such notice shall specify the date the
generating facility will be ready for interconnection, the date the generating
facility will be able to commence testing, and the anticipated date of
operation after testing. The interconnection customer shall pay the estimated
costs of interconnection in full at the time the notice to interconnect is
given. The utility shall pay an interconnection customer for any energy
produced during testing of the generating facility at the appropriate energy
rate pursuant to Subsection B of
17.9.570.11 NMAC.
G. If the utility determines that it cannot
interconnect the generating facility within the time set in the notice to
interconnect because adequate interconnection facilities are not available, it
shall, within 15 business days of receipt of the notice to interconnect, notify
the interconnection customer specifying the reasons it cannot interconnect as
requested by the interconnection customer and specifying the date
interconnection can be made. If the interconnection customer objects to the
date for interconnection specified by the utility, objects to the utility's
determination that adequate interconnection facilities are not available, or
disputes the good faith efforts of the utility to interconnect, the
interconnection customer may initiate a proceeding before the commission
pursuant to the complaint process of 17.9.570 NMAC.
H. Payment for all costs of interconnection
shall be the responsibility of the interconnection customer. If the utility
incurs any of the costs of interconnection, the interconnection customer shall
reimburse the utility for such costs. The estimated costs for interconnection
described in this rule 17.9.569 NMAC shall be paid prior to interconnection.
Upon completion of the interconnection the actual costs of interconnection
shall be determined in a verifiable form by the utility, and any actual costs
in excess of the estimated costs shall be paid by the interconnection customer
to the utility within 30 days. If the estimated costs exceed actual costs the
utility shall refund the difference to the interconnection customer within 30
days.
I. Each utility shall develop
and file with the commission proposed general safety standards governing the
installation, operation, and maintenance of the protective equipment required
to integrate generating facilities subject to this rule 17.9.569 NMAC into the
utility's electric system (if any such equipment is required). These general
safety standards may contain reasonable provisions for case-by-case standards
for certain generation facilities based on their size or location. These
standards shall be reasonable and nondiscriminatory and shall be designed to
assure system and personnel safety.
J. The generating facility's output to the
utility will meet the following interconnection standards.
(1) The voltage will be that voltage normally
available on the utility system at the generator's site or such other standard
voltage to which the parties may agree.
(2) The frequency will be 60 hertz.
(3) The number of phases of the produced
voltage will be compatible with the phases available on the utility system at
the generator site. Normally the number of phases shall be the same as those of
the utility system.
(4) The
protective devices connected between the output of the generating facility and
the utility system must be rated for the maximum available fault current that
the utility's system may be capable of developing at the point of
interconnection. Such devices shall disconnect the generating facility's
generation from the utility's system in the event of a fault on the generating
facility system in order to maintain continuity of service to other customers
connected to the secondary of the distribution transformer or other portions of
the utility's system.
(5) The
generating facility's output shall not affect the utility's distribution
system. This includes but is not limited to:
(a) overload of distribution
equipment;
(b) abnormal harmonic
currents or voltages;
(c)
interference with automatic voltage regulation equipment; and
(d) electronic noise that would interfere
with communications.
(6)
The generating facility shall be capable of protecting itself from damage
resulting from impact loading and/or overloading under both normal operating
conditions and emergency conditions.
K. Interconnection and safety requirements
shall include the ability to synchronize on connecting to the utility system to
avoid voltage decay or out-of-phase connection. The generating facility's
controls shall be capable of disconnecting the generation output to the utility
or otherwise limiting the generating facility's input to avoid overload of any
of the utility system components or undesirable transient voltage or frequency
fluctuations in the event of a fault on the utility's system or under
conditions of large motor start or capacitor switching operations on the
utility system to which the generating facility is interconnected. These
devices must be coordinated with the utility's protective system. The
generating facility must meet the following safety standards.
(1) The generating facility's interconnection
must meet the requirements of the latest editions of the national electrical
safety code, national electrical code, and the state of New Mexico electrical
code.
(2) The generating facility's
interconnection must automatically disconnect from the utility's system if the
utility service is interrupted. The generating facility will coordinate
automatic reenergization in the utility's system with the utility's standard
protection practices. The utility may discontinue service to or from a
generating facility if it has been determined that continuation of service
would contribute to such emergency.
(3) There must be a three-phase load break
disconnect between the generating facility's interconnection and the utility
that can be controlled and operated by the utility.
(a) Where the generating facility is a
customer of the utility, the disconnect or disconnects shall disconnect the
generating facility's output without interrupting utility service to the
customer's other load unless otherwise agreed.
(b) The disconnect must provide a visible air
gap which will assure disconnection of the generating facility before a utility
employee does any work on the circuit or circuits to which the interconnection
is made.
(c) The meter socket or
secondary connection compartment or bus compartment may be provided by the
utility or provision may be required of the interconnection customer as is
presently provided for in the case of each component by the rules and
regulations filed with the commission in the case of the specific
utility.
(d) In any event the
capacity and the connection arrangements of the specific device must be
approved by the utility if the generating facility is required to provide the
device.
L. A
utility may require that an interconnection customer provide proof of insurance
or other evidence of financial responsibility in an amount reasonably related
to the risks involved.