N.M. Admin. Code § 17.9.592.10 - CONTENTS OF APPLICATION FOR LOCATION APPROVAL OF TRANSMISSION LINE
A person seeking to construct a transmission line shall file with the commission an application for approval of location, supported by written direct testimony and supporting exhibits, which shall contain:
A. a description of the transmission line
including, but not limited to:
(1) the
location of the transmission line and a map depicting the location in
electronic format and physical format with a scale not to exceed one inch
equals five miles;
(2)
identification of the ownership of the land (such as private, bureau of land
management, U.S. forest service, state trust, etc.) the transmission line will
cross, and the number of feet the transmission line will cross over each
owner's land;
(3) the total length
of each transmission line in feet;
(4) a description of interconnection
facilities; and
(5) a schematic
diagram showing the transmission line and the interconnection of the
transmission line to the transmission grid;
B. identification of all applicable land use
statutes and administrative regulations, and proof of compliance or statement
of noncompliance with each;
C. if
required under NEPA, an environmental assessment prepared in connection with
the transmission line;
D. if
required under NEPA, an environmental impact statement and record of decision,
or a finding of no significant impact, prepared in connection with the
transmission line;
E. if
preparation of a federal environmental assessment or environmental impact
statement is not required under NEPA in connection with the transmission line,
then a report, comparable to an environmental impact statement, in the format
prescribed in 40 C.F.R.
Section 1502.10;
F. all written federal, state, and local
environmental authorizations necessary to begin construction, and necessary to
begin operation, of the transmission line; if any such authorization cannot be
obtained until after construction of the transmission line, proof of
application for such authorization;
G. testimony demonstrating that the
transmission line will not unduly impair important environmental values;
important environmental values include, but are not limited to:
(1) preservation of air quality and water
quality;
(2) preservation of land
uses, soils, flora, and fauna; and
(3) preservation of water resources, mineral
resources, socioeconomic resources, cultural resources, historic resources,
religious resources, visual resources, geologic resources, and geographic
resources.
H. the
expected date that the transmission line will be online;
I. proof that the application has been served
on all local authorities in each county and township where the transmission
line will be located, the New Mexico attorney general, the New Mexico
environment department, and the New Mexico state engineer; and
J. any other information, including
photographs, which the applicant wishes to submit in support of the
application.