Ohio Admin. Code 3745-256-102 - Closure and post-closure care of containment buildings
(A) At closure of a
containment building, the owner or operator must remove or decontaminate all
waste residues, contaminated containment system components (liners, etc.),
contaminated subsoils, and structures and equipment contaminated with waste and
leachate, and manage them as hazardous waste unless paragraph (D) of rule
3745-51-03 of the Administrative
Code applies. The closure plan, closure activities, cost estimates for closure,
and financial responsibility for containment buildings must meet all of the
requirements specified in rules
3745-66-10 to
3745-66-21 and
3745-66-40 to
3745-66-48 of the Administrative
Code.
(B) If, after removing or
decontaminating all residues and making all reasonable efforts to effect
removal or decontamination of contaminated components, subsoils, structures,
and equipment as required in paragraph (A) of this rule, the owner or operator
finds that not all contaminated subsoils can be practicably removed or
decontaminated, he must close the facility and perform post-closure care in
accordance with the closure and post-closure requirements that apply to
landfills (rule
3745-68-10 of the Administrative
Code). In addition, for the purposes of closure, post-closure, and financial
responsibility, such a containment building is then considered to be a landfill
and the owner or operator must meet all of the requirements for landfills
specified in rules
3745-66-10 to
3745-66-21 and
3745-66-40 to
3745-66-48 of the Administrative
Code.
Notes
Rule promulgated under: RC 119.03
Rule authorized by: RC 3734.12
Rule amplifies: RC 3734.12
RC 119.032 Review Date: Exempt
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.