(1) The EDU shall approve an application for
interconnection under level 2 review procedures if the DER meets the following
criteria:
(a) The proposed DER's point of
common coupling is not on a transmission line.
(b) The proposed DER complies with applicable
codes and standards, effective as set forth in rule
4901:1-22-03 of the
Administrative Code.
(c) The
proposed DER is not located in an area where there are known or posted
transient stability limitations to generating units located in the general
electrical vicinity (for example, three or four distribution busses from the
point of interconnection), or the proposed DER shall not have
interdependencies, known to the EDU, with earlier queued transmission system
interconnection requests. The EDU shall not disclose confidential information
in the application of this screen.
(d) For interconnection of a proposed DER to
a radial distribution circuit, the aggregated generation, including the
proposed DER, on the circuit shall not exceed fifteen per cent of the line
section annual peak load as most recently measured at the substation. The
application of this screen addresses back feed and islanding
conditions.
(e) The proposed DER,
in aggregation with other DER generation on the distribution circuit, shall not
contribute more than ten per cent to the distribution circuit's maximum fault
current at the point on the primary voltage distribution line nearest the point
of common coupling.
(f) The
proposed DER, in aggregation with other DER generation on the distribution
circuit, may not cause any distribution protective devices and equipment
including substation breakers, fuse cutouts, and line reclosers, or other
customer equipment on the electric distribution system, to be exposed to fault
currents exceeding ninety per cent of the short circuit interrupting
capability; nor shall an application requesting interconnection on a circuit
that already exceeds ninety per cent of the short circuit interrupting
capability be approved.
(g) When a
proposed DER is single phase and is to be interconnected on a center tap
neutral of a two hundred forty volt service, its addition shall not create an
imbalance between the two sides of the two hundred forty volt service of more
than twenty per cent of the nameplate rating of the service
transformer.
(h) The proposed DER
shall be interconnected to the EDU's primary distribution system as shown:
|
Primary Distribution Line Configuration
|
Interconnection to Primary Distribution
Line
|
|
Three phase, three wire
|
If a three-phase or single-phase DER, interconnection
must be phase-to-phase
|
|
Three phase, four wire
|
If a three-phase (effectively grounded) or single phase
DER, interconnection must be line-to-neutral
|
(i) A
review of the type of electrical service provided to the applicant, including
line configuration and the transformer connection, will be conducted to limit
the potential for creating over voltages on the EDU's electric distribution
system due to a loss of ground during the operating time of any anti-islanding
function.
(j) When the proposed DER
is to be interconnected on single-phase shared secondary line, the aggregate
DER generation capacity on the shared secondary line, including the proposed
DER, will not exceed sixty-five per cent of the transformer nameplate
rating.
(k) For interconnection of
a proposed DER to the load side of spot or area network protectors, the
proposed DER must utilize an inverter-based equipment package and, aggregated
with other inverter-based generation, shall not exceed the lesser of five per
cent of a spot or area network's maximum load or fifty kilowatts.
(l) Construction of facilities by the EDU on
its own system is not required to accommodate the DER.