Or. Admin. R. 123-027-0056 - Federally Authorized Project Application Requirements
The Port shall notify the Authority of a potential federally authorized project at the time it initiates the project with the United States Army Corps of Engineers and it shall submit written documentation to the Authority evidencing its participation with the United States Army Corps of Engineers. The written documentation must:
(1) Describe the nature and purpose of the
project, including: proposed project scheduling; project term; estimated
project cost; the Port's estimated non-federal share of the total project cost;
and, the required schedule for payment of the Port's non-federal share of the
total project cost;
(2) Contain
federal documents that authorize the project, including
Reconnaissance/Feasibility Studies; and
(3) Contain a copy of the Port's proposed
Local Cost Share Agreement with the United States Army Corps of Engineers for
undertaking and carrying out the project.
Notes
Stat. Auth.: ORS 285A.075
Stats. Implemented: ORS 777.262 - 777.267