Or. Admin. Code § 137-049-0250 - Addenda to Solicitation Documents
(1)
Issuance; Receipt. The
Contracting Agency may change a Solicitation Document only by Written Addenda.
An Offeror shall provide Written acknowledgement of receipt of all issued
Addenda with its Offer, unless the Contracting Agency otherwise specifies in
the Addenda or in the Solicitation Document.
(2)
Notice and Distribution. The
Contracting Agency shall notify prospective Offerors of Addenda consistent with
the standards of Notice set forth in OAR 137-049-0210(1). The Solicitation
Document shall specify how the Contracting Agency will provide notice of
Addenda and how the Contracting Agency will make the Addenda available (see,
137-049-0200(1)(a)(N). For example, "Contracting Agency will not mail notice of
Addenda, but will publish notice of any Addenda on Contracting Agency's Web
site. Addenda may be downloaded off the Contracting Agency's Web site. Offerors
should frequently check the Contracting Agency's Web site until closing, i.e.,
at least once weekly until the week of Closing and at least once daily the week
of the Closing."
(3)
Timelines; Extensions. The Contracting Agency shall issue Addenda
within a reasonable time to allow prospective Offerors to consider the Addenda
in preparing their Offers. The Contracting Agency may extend the Closing if the
Contracting Agency determines prospective Offerors need additional time to
review and respond to Addenda. Except to the extent required by public
interest, the Contracting Agency shall not issue Addenda less than 72 hours
before the Closing unless the Addendum also extends the Closing.
(4)
Request for Change or
Protest. Unless a different deadline is set forth in the Addendum, an
Offeror may submit a Written request for change or protest to the Addendum, as
provided in OAR 137-049-0260, by the close of the Contracting Agency's next
business day after issuance of the Addendum, or up to the last day allowed to
submit a request for change or protest under 137-049-0260, whichever date is
later. The Contracting Agency shall consider only an Offeror's request for
change or protest to the Addendum; the Contracting Agency shall not consider a
request for change or protest to matters not added or modified by the Addendum,
unless the Offeror submits the request for change or protest before the
deadline for the Contracting Agency's receipt of request for change or protests
as set forth in 137-049-0260(2) and (3).
Notes
Stat. Auth.: ORS 279A.065
Stats. Implemented: ORS 279C.395 & 279A.065
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.