Or. Admin. Code § 141-089-0695 - Piling Placement And Removal Within ESH - Activity-Specific Conditions
Projects eligible for this GA must adhere to the general conditions in OAR 141-089-0650 and the following activity-specific conditions:
(1) Minimum Necessary.
Number of pilings must be the minimum necessary to fulfill the essential
purpose.
(2) Sound Attenuation. A
vibratory hammer must be used whenever feasible. If an impact hammer must be
used to drive or proof steel piles, sound attenuation measures including
cushion blocks (wood blocks between pile and hammer) and bubble curtains
operated to distribute air bubbles around 100 percent of the piling for the
full depth of the water column must be used:
(a) If water velocity is 1.7 miles per hour
or less, an unconfined bubble curtain may be used; or
(b) If water velocity is greater than 1.7
miles per hour, a confined bubble curtain (e.g., bubble ring surrounded by
fabric or metal sleeve) must be used.
(3) Method for Removal of Piling. Removal of
piling must be conducted using a vibratory method:
(a) Piling must not intentionally be broken
by twisting or bending;
(b) Upon
removal, piling must be handled to effectively contain all adhering sediment.
All return flows must meet state water quality standards; and
(c) Piling and containment materials must be
disposed in an approved upland disposal site.
(4) Removal Problems in Uncontaminated
Sediment. If wood piling breaks above or below the bed surface within an area
of uncontaminated sediment, piling must be cut at least three feet below the
bed surface or otherwise pushed into that depth, then covered with a cap of
clean substrate.
(5) Removal
Problems in Contaminated Sediment. If wood piling breaks above the bed surface
within an area of known contaminated sediment, piling must be cut at the bed
surface or otherwise pushed to that depth. If piling breaks in contaminated
sediment below the bed surface, no further attempt at removal may be made and
the hole must be covered with a cap of clean substrate.
(6) Prevent Perching. Piling must be fitted
with devices to effectively prevent perching by fish-eating bird
species.
(7) Barge or Top of Bank
Position. Piling must be placed or removed from a barge-mounted or above
top-of-bank position. If barge-mounted, barge must not at any time be grounded
in the bed or banks.
Notes
Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990
Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.795 - 196.990