Or. Admin. Code § 340-120-0005 - Permitting Procedure
(1) A three step
permitting procedure is required for facilities listed in OAR
340-120-0001(2).
The three steps are:
(a) Submit a request for
and obtain an Authorization to Proceed from the Department;
(b) Submit a request for and obtain a Land
Use Compatibility Statement from the local government with land use
jurisdiction or as applicable, from the Department; and
(c) Submit a complete application for and
obtain a treatment or disposal permit pursuant to Divisions 105, 106 and 110 of
this Chapter from the Department, or as applicable, from the
Commission.
(2) An
initial period is established during which the Department shall accept requests
for an Authorization to Proceed. The initial period begins May 15, 1986 and
ends January 1, 1987. The Department shall wait until at least the end of the
initial period before approving or denying any of the requests.
(3) Requests for an Authorization to Proceed
received by the Department after January 1, 1987 must include information to
allow the Commission to find there is a need for a new facility. The Department
cannot approve an Authorization to Proceed request received after January 1,
1987 until the Commission makes this finding.
(4) Each request for an Authorization to
Proceed will be reviewed for completeness by the Department within 90 days of
its receipt. If an applicant fails to correct deficiencies within 90 days of
written notice from the Department, the Department may deny the
request.
(5) After obtaining an
Authorization to Proceed and a Land Use Compatibility Statement, an applicant
may apply for a hazardous waste or PCB treatment or disposal permit pursuant to
Divisions 105, 106 and 110 of this Chapter.
(6) To retain an Authorization to Proceed, an
applicant shall:
(a) Submit a request to the
appropriate planning jurisdiction for the Land Use compatibility Statement
within 90 days of issuance of the Authorization to Proceed;
(b) Submit an application for a treatment or
disposal permit to the Department within 6 months of issuance of the Land Use
Compatibility Statement.
(7) If the Department or Commission denies
the permit, the Authorization to Proceed is revoked.
(8) The owner of an existing facility with an
effective permit must reapply according to the provisions of OAR
340-105-0010(4)
before the expiration of the existing
permit. Upon reapplication:
(a) The applicant
of a facility described in OAR
340-120-0001(2)
shall demonstrate the criteria of OAR
340-120-0010(2)(a)(A), (b)(B), (b)(C), (c), (e),
(g) and (h) and
340-120-0025 are being
met.
(b) The applicant of a
facility described in OAR
340-120-0001(4)
shall demonstrate that the Property Line
Setback criterion of OAR
340-120-0010(2)(e)
is being met.
(9) The Property Line Setback criterion of
OAR 340-120-0010(2)(e)
shall apply to the existing Chem-Security
Systems, Inc., hazardous waste and PCB disposal facility eight years from the
effective date of this rule.
COMMENT:Section 9 of this rule does not pertain to or determine the duration of any permit issued by the Commission to Chem-Security in response to the application for a permit pending before the Commission on the effective date of this rule.
Notes
Stat. Auth: ORS 466 &ORS 468ORS
Stats. Implemented:ORS 466.035,ORS 466.040ORS466.045 & 468.020