(1) An
"administrative permit amendment" is a permit revision that:
(a) Corrects typographical errors;
(b) Identifies a change in the name, address,
or phone number of the responsible official identified in the permit, or
provides a similar minor administrative change at the source;
(c) Allows for a change in the name of the
permittee;
(d) Allows for a change
in ownership or operational control of a source where DEQ determines that no
other change in the permit is necessary, provided that a written agreement
containing a specific date for transfer of permit responsibility, coverage, and
liability between the current and new permittee has been submitted to
DEQ;
(e) Requires more frequent
monitoring or reporting by the permittee;
(f) Allows for a change in the date for
reporting or source testing requirements for a source or emissions unit that is
temporarily shut down or would otherwise have to be operated solely for the
purposes of conducting the source test, except when required by a compliance
schedule;
(g) Relaxes monitoring,
reporting or recordkeeping due to a permanent source shutdown for only the
emissions unit being shut down; or
(h) Incorporates into the Oregon Title V
Operating Permit the requirements from preconstruction review permits
authorized under OAR 340 division 224 or OAR
340-210-0205 through
340-210-0250, provided that the
procedural requirements followed in the preconstruction review are
substantially equivalent to the requirements of
340-218-0120 through
340-218-0210 and
340-218-0230 that would be
applicable to the change if it were subject to review as a permit modification,
compliance requirements are substantially equivalent to those contained in
340-218-0050 through
340-218-0110, and no changes in
the construction or operation of the facility that would require a permit
modification under 340-218-0160 through
340-218-0180 have taken
place.
(2) Administrative
permit amendments for purposes of the national acid rain portion of the permit
will be governed by regulations promulgated under Title IV of the
FCAA.
(3) Administrative permit
amendment procedures. An administrative permit amendment will be made by DEQ
consistent with the following:
(a) The owner
or operator must promptly submit an application for an administrative permit
amendment upon becoming aware of the need for one on forms provided by DEQ
along with a copy of the draft amendment;
(b) DEQ will take no more than 60 days from
receipt of a request for an administrative permit amendment to take final
action on such request, and may incorporate such changes without providing
notice to the public or affected States provided that it designates any such
permit revisions as having been made pursuant to this rule;
(c) DEQ will issue the administrative permit
amendment in the form of a permit addendum for only those conditions that will
change;
(d) DEQ will submit a copy
of the permit addendum to the EPA;
(e) The source may implement the changes
addressed in the request for an administrative amendment immediately upon
submittal of the request;
(f) If
the source fails to comply with its draft permit terms and conditions upon
submittal of the application and until DEQ takes final action, the existing
permit terms and conditions it seeks to modify may be enforced against
it.
(4) DEQ must, upon
taking final action granting a request for an administrative permit amendment,
allow coverage by the permit shield in OAR
340-218-0110 only for
administrative permit amendments made pursuant to
340-218-0150(1)(h)
which meet the relevant requirements of
340-218-0050 through
340-218-0240 for significant
permit modifications.
(5) If it
becomes necessary for DEQ to initiate an administrative amendment to the
permit, DEQ will notify the permittee of the intended action by certified or
registered mail. The action will become effective 20 days after the date of
mailing unless within that time the permittee makes a written request for a
hearing. The request must state the grounds for the hearing. Any hearing held
will be conducted pursuant to the applicable provisions of ORS 183.
Notes
Statutory/Other Authority: ORS 468.020, 468A.025, 468A.040 & 468A.310
Statutes/Other Implemented: ORS 468A
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.