Or. Admin. Code § 340-218-0190 - Construction/Operation Modifications
(1) Notice
of Approval. The owner or operator of a major stationary source must obtain
approval from the Department prior to construction or modification of any
stationary source or air pollution control equipment in accordance with OAR
340-210-0205 through
340-210-0250.
(2) Incorporation into an Oregon Title V
Operating Permit:
(a) Where an Oregon Title V
Operating Permit would allow incorporation of such construction or modification
as an off-permit change (OAR
340-218-0140(2))
or a FCAA section 502(b)(10) change (340-218-0140(3)):
(A) The owner or operator of the stationary
source or air pollution control equipment listed in section(1) of this rule
must submit to the Department the applicable notice; and
(B) The Department will incorporate the
construction or modification at permit renewal, if applicable.
(b) Where an Oregon Title V
Operating Permit would allow incorporation of such construction or modification
as an administrative amendment (OAR
340-218-0150), the owner or
operator of the stationary source or air pollution control equipment listed in
section (1) of this rule may:
(A) Submit the
permit application information required under OAR
340-218-0150(3)
with the information required under
340-210-0225(2)
upon becoming aware of the need for an
administrative amendment; and
(B)
Request that the external review procedures required under OAR
340-218-0210 and
340-218-0230 be used in addition
to the public notice procedures of OAR 340 division 209 for Category III permit
actions to allow for subsequent incorporation of the construction permit as an
administrative amendment.
(c) Where an Oregon Title V Operating Permit
would require incorporation of such construction or modification as a minor
permit modification (OAR
340-218-0170) or a significant
permit modification (340-218-0180), the owner or
operator of the stationary source or air pollution control equipment listed in
section(1) of this rule must submit the permit application information required
under 340-218-0040(3)
within one year of initial startup of the
construction or modification, except as prohibited in paragraph(2)(d) of this
rule.
(d) Where an existing Oregon
Title V Operating Permit would prohibit such construction or change in
operation, the owner or operator must obtain a permit revision before
commencing operation.
NOTE: This rule is included in the State of Oregon Clean Air Act Implementation Plan as adopted by the EQC under OAR 340-200-0040.
Notes
Stat. Auth.: ORS 468 & 468A
Stats. Implemented: ORS 468 & 468A
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.