(1) The standards under OAR
340-230-0300 through 0359 apply
at all times except during periods of startup, shutdown, and malfunction.
Duration of startup, shutdown, or malfunction periods are limited to 3 hours
per occurrence, except as provided in subsection (1)(c) of this rule. During
periods of startup, shutdown, or malfunction, monitoring data must be dismissed
or excluded from compliance calculations, but must be recorded and reported in
accordance with the provisions of OAR
340-230-0350(1)(f).
(a) The startup period commences when the
affected facility begins the continuous burning of municipal solid waste and
does not include any warmup period when the affected facility is combusting
fossil fuel or other non municipal solid waste fuel, and no municipal solid
waste is being fed to the combustor.
(b) Continuous burning is the continuous,
semicontinuous, or batch feeding of municipal solid waste for purposes of waste
disposal, energy production, or providing heat to the combustion system in
preparation for waste disposal or energy production. The use of municipal solid
waste solely to provide thermal protection of the grate or hearth during the
startup period when municipal solid waste is not being fed to the grate is not
considered to be continuous burning.
(c) For purposes of compliance with the
carbon monoxide emissions limit in OAR
340-230-320(1), if a loss of boiler
water level control (e.g., boiler waterwall tube failure) or a loss of
combustion air control (e.g., loss of combustion air fan, induced draft fan,
combustion grate bar failure) is determined to be a malfunction, the duration
of the malfunction period is limited to 15 hours per occurrence. During such
periods of malfunction, monitoring data must be dismissed or excluded from
compliance calculations, but must be recorded and reported in accordance with
the provisions of OAR
340-230-0350(1)(f).
(2) The owner or operator of an
affected facility must install, calibrate, maintain, and operate a continuous
emission monitoring system for measuring the oxygen or carbon dioxide content
of the flue gas at each location where carbon monoxide, sulfur dioxide, or
nitrogen oxides emissions, or particulate matter (if the owner or operator
elects to continuously monitor emissions under section (13) of this rule) are
monitored and record the output of the system and must comply with the test
procedures and test methods specified in subsections (2)(a) through (g) of this
rule.
(a) The span value of the oxygen (or
carbon dioxide) monitor must be 25 percent oxygen (or 20 percent carbon
dioxide).
(b) The monitor must be
installed, evaluated, and operated in accordance with
40 CFR
60.13.
(c) The monitor must conform to Performance
Specification 3 in appendix B of 40 CFR
60 except for section 2.3 (relative
accuracy requirement).
(d) The
quality assurance procedures of Appendix F of 40 CFR
60 except for section
5.1.1 (relative accuracy test audit) shall apply to the monitor.
(e) If carbon dioxide is selected for use in
diluent corrections, the relationship between oxygen and carbon dioxide levels
must be established during the initial performance test according to the
following procedures and methods specified in paragraphs (2)(e)(A) through (D)
of this rule. This relationship may be reestablished during subsequent
performance compliance tests.
(A) The fuel
factor equation in Method 3B must be used to determine the relationship between
oxygen and carbon dioxide at a sampling location. EPA Reference Method 3, 3A,
3B, or as an alternative ASME PTC-19-10-1981-Part 10, as applicable, must be
used to determine the oxygen concentration at the same location as the carbon
dioxide monitor.
(B) Samples must
be taken for at least 30 minutes in each hour.
(C) Each sample must represent a 1-hour
average.
(D) A minimum of three
runs must be performed.
(f) The relationship between carbon dioxide
and oxygen concentrations that is established in accordance with subsection
(2)(e) of this rule must be submitted to the Department as part of the annual
performance test report if the relationship is reestablished during the annual
performance test.
(g) During a loss
of boiler water level control or loss of combustion air control malfunction
period as specified in subsection (1)(c) of this rule, a diluent cap of 14
percent for oxygen or 5 percent for carbon dioxide may be used in the emissions
calculations for sulfur dioxide and nitrogen oxides.
(3) Except as provided in subsection (3)(i)
of this rule, the procedures and test methods specified in subsections (3)(a)
through (j) of this rule must be used to determine compliance with the emission
limits for particulate matter and opacity under OAR
340-230-0310(1) and
(2).
(a)
EPA Reference Method 1 must be used to select sampling site and number of
traverse points.
(b) EPA Reference
Method 3, 3A or 3B, or as an alternative ASME PTC-19-10-1981-Part 10, as
applicable, must be used for gas analysis.
(c) EPA Reference Method 5 must be used for
determining compliance with the particulate matter emission limit. The minimum
sample volume must be 1.7 cubic meters (60 cubic feet). The probe and filter
holder heating systems in the sample train must be set to provide a gas
temperature no greater than 160°C (320°F). An oxygen or carbon dioxide
measurement must be obtained simultaneously with each EPA Reference Method 5
run.
(d) The owner or operator of
an affected facility may request that compliance with the particulate matter
emission limit be determined using carbon dioxide measurements corrected to an
equivalent of 7 percent oxygen. The relationship between oxygen and carbon
dioxide levels for the affected facility must be established as specified in
subsection (2)(e) of this rule.
(e)
As specified under
40 CFR
60.8,
all performance tests must consist of at least three test runs. The average of
the particulate matter emission concentrations from the three test runs is used
to determine compliance.
(f) In
accordance with subsections (3)(g) and (j) of this rule, EPA Reference Method 9
must be used for determining compliance with the opacity limit except as
provided under
40 CFR
60.11(e).
(g) The owner or operator of an affected
facility must install, calibrate, maintain, and operate a continuous opacity
monitoring system for measuring opacity and must follow the methods and
procedures specified in paragraphs (3)(g)(A) through (C) of this rule.
(A) The output of the continuous opacity
monitoring system must be recorded on a 6-minute average basis.
(B) The continuous opacity monitoring system
must be installed, evaluated, and operated in accordance with
40 CFR
60.13.
(C) The continuous opacity monitoring system
must conform to Performance Specification 1 in Appendix B of 40 CFR Part
60.
(h) The owner or
operator of an affected facility must conduct a performance test for
particulate matter on a calendar year basis (no less than 9 calendar months and
no more than 15 calendar months following the previous performance test; and
must complete five performance tests in each 5-year calendar period).
(i) In place of particulate matter testing
with EPA Reference Method 5, an owner or operator may elect to install,
calibrate, maintain, and operate a continuous emission monitoring system for
monitoring particulate matter emissions discharged to the atmosphere and record
the output of the system. The owner or operator of an affected facility who
elects to continuously monitor particulate matter emissions instead of
conducting performance testing using EPA Reference Method 5 must install,
calibrate, maintain, and operate a continuous emission monitoring system and
must comply with the requirements specified in paragraphs (3)(i)(A) through (N)
of this rule. The owner or operator who elects to continuously monitor
particulate matter emissions instead of conducting performance testing using
EPA Reference Method 5 is not required to complete performance testing for
particulate matter as specified in subsection (3)(h) of this rule and is not
required to continuously monitor opacity as specified in subsection (3)(g) of
this rule.
(A) Notify the Administrator and
the Department one month before starting use of the system.
(B) Notify the Administrator and the
Department one month before stopping use of the system.
(C) The monitor must be installed, evaluated,
and operated in accordance with
40 CFR
60.13.
(D) The initial performance evaluation must
be completed no later than 180 days of notification to the Administrator and
the Department of use of the continuous monitoring system if the owner or
operator was previously determining compliance by Method 5 performance tests,
whichever is later.
(E) The owner
or operator of an affected facility may request that compliance with the
particulate matter emission limit be determined using carbon dioxide
measurements corrected to an equivalent of 7 percent oxygen. The relationship
between oxygen and carbon dioxide levels for the affected facility must be
established as specified in subsection (2)(e) of this rule.
(F) The owner or operator of an affected
facility must conduct an initial performance test for particulate matter
emissions as required under
40 CFR
60.8.
Compliance with the particulate matter emission limit must be determined by
using the continuous emission monitoring system specified in subsection (3)(i)
of this rule to measure particulate matter and calculating a 24-hour block
arithmetic average emission concentration using EPA Reference Method 19,
section 12.4.1.
(G) Compliance with
the particulate matter emission limit must be determined based on the 24-hour
daily (block) average of the hourly arithmetic average emission concentrations
using continuous emission monitoring system outlet data.
(H) At a minimum, valid continuous monitoring
system hourly averages must be obtained as specified in subparagraphs
(3)(i)(H)(i) and (ii) of this rule for at least 90 percent of the operating
hours per calendar quarter and 95 percent of the operating hours per calendar
year that the affected facility is combusting municipal solid waste.
(i) At least two data points per hour must be
used to calculate each 1-hour arithmetic average.
(ii) Each particulate matter 1-hour
arithmetic average must be corrected to 7 percent oxygen on an hourly basis
using the 1-hour arithmetic average of the oxygen (or carbon dioxide)
continuous emission monitoring system data.
(I) The 1-hour arithmetic averages required
under paragraph (3)(i)(G) of this rule must be expressed in milligrams per dry
standard cubic meter corrected to 7 percent oxygen (dry basis) and must be used
to calculate the 24-hour daily arithmetic average emission concentrations. The
1-hour arithmetic averages must be calculated using the data points required
under
40 CFR
60.13(e)(2).
(J) All valid continuous emission monitoring
system data must be used in calculating average emission concentrations even if
the minimum continuous emission monitoring system data requirements of
paragraph (3)(i)(H) of this rule are not met.
(K) The continuous emission monitoring system
must be operated according to Performance Specification 11 in 40 CFR part
60
appendix B.
(L) During each
relative accuracy test run of the continuous emission monitoring system
required by Performance Specification 11 in 40 CFR part
60 appendix B,
particulate matter and oxygen (or carbon dioxide) data must be collected
concurrently (or within a 30- to 60-minute period) by both the continuous
emission monitors and the test methods specified in subparagraphs (3)(i)(L)(i)
and (ii) of this rule.
(i) For particulate
matter, EPA Reference Method 5 must be used.
(ii) For oxygen (or carbon dioxide), EPA
Reference Method 3, 3A, or 3B, as applicable must be used.
(M) Quarterly accuracy determinations and
daily calibration drift tests must be performed in accordance with Procedure 2
in 40 CFR part
60 appendix F.
(N)
When particulate matter emissions data are not obtained because of continuous
emission monitoring system breakdowns, repairs, calibration checks, and zero
and span adjustments, emissions data must be obtained by using other monitoring
systems as approved by the Administrator or EPA Reference Method 19 to provide,
as necessary, valid emissions data for a minimum of 90 percent of the hours per
calendar quarter and 95 percent of the hours per calendar year that the
affected facility is operated and combusting municipal solid waste.
(j) For each affected facility,
the owner or operator must conduct a performance test for opacity on an annual
basis (no less than 9 calendar months and no more than 15 calendar months
following the previous performance test; and must complete five performance
tests in each 5-year calendar period) using the test method specified in
subsection (3)(f) of this rule.
(4) The procedures and test methods specified
in subsections (4)(a) and (b) of this rule must be used to determine compliance
with the emission limits for cadmium, lead, and mercury under OAR
340-230-0310(3).
(a) The procedures and test methods specified
in paragraphs (4)(a)(A) through (G) of this rule must be used to determine
compliance with the emission limits for cadmium and lead under OAR
340-230-0310(3)(a) and
(b).
(A)
EPA Reference Method 1 must be used for determining the location and number of
sampling points.
(B) EPA Reference
Method 3, 3A, or 3B, or as an alternative ASME PTC-19-10-1981-Part 10, as
applicable, must be used for flue gas analysis.
(C) EPA Reference Method 29 must be used for
determining compliance with the cadmium and lead emission limits.
(D) An oxygen or carbon dioxide measurement
must be obtained simultaneously with each EPA Reference Method 29 test run for
cadmium and lead required under paragraph (4)(a)(C) of this rule.
(E) The owner or operator of an affected
facility may request that compliance with the cadmium or lead emission limit be
determined using carbon dioxide measurements corrected to an equivalent of 7
percent oxygen. The relationship between oxygen and carbon dioxide levels for
the affected facility must be established as specified in subsection (2)(e) of
this rule.
(F) All performance
tests must consist of at least three test runs conducted under representative
full load operating conditions. The average of the cadmium and lead emission
concentrations from three test runs or more must be used to determine
compliance.
(G) The owner or
operator of an affected facility must conduct a performance test for compliance
with the emission limits for cadmium and lead on a calendar year basis (no less
than 9 calendar months and no more than 15 calendar months following the
previous performance test; and must complete five performance tests in each
5-year calendar period).
(b) The procedures and test methods specified
in paragraphs (4)(b)(A) through (I) of this rule must be used to determine
compliance with the mercury emission limit under OAR
340-230-0310(3)(c).
(A) EPA Reference Method 1 must be used for
determining the location and number of sampling points.
(B) EPA Reference Method 3, 3A, or 3B, or as
an alternative ASME PTC-19-10-1981-Part 10, as applicable, must be used for
flue gas analysis.
(C) EPA
Reference Method 29 or as an alternative ASTM D6784-02 must be used to
determine the mercury emission concentration. The minimum sample volume when
using EPA Reference Method 29 or as an alternative ASTM D6784-02 for mercury is
1.7 cubic meters (60 cubic feet).
(D) An oxygen (or carbon dioxide) measurement
must be obtained simultaneously with each EPA Reference Method 29 or as an
alternative ASTM D6784-02 test run for mercury required under paragraph
(4)(b)(C) of this rule.
(E) The
percent reduction in the potential mercury emissions (%PHg) is computed using
equation 1: [Equation not included. See NOTE.]
(F) All performance tests must consist of a
minimum of three test runs conducted under representative full load operating
conditions. The average of the mercury emission concentrations or percent
reductions from three test runs or more is used to determine
compliance.
(G) The owner or
operator of an affected source may request that compliance with the mercury
emission limit be determined using carbon dioxide measurements corrected to an
equivalent of 7 percent oxygen. The relationship between oxygen and carbon
dioxide levels for the affected facility must be established as specified in
subsection (2)(e) of this rule.
(H)
The owner or operator of an affected facility must conduct a performance test
for mercury emissions on a calendar year basis (no less than 9 calendar months
and no more than 15 calendar months from the previous performance test; and
must complete five performance tests in each 5-year calendar period).
(I) The owner or operator of an affected
facility where activated carbon injection is used to comply with the mercury
emission limit must follow the procedures specified in section (12) of this
rule for measuring and calculating carbon usage.
(c) testing with EPA Reference Method 29 or
as an alternative ASTM D6784-02, an owner or operator may elect to install,
calibrate, maintain, and operate a continuous emission monitoring system for
monitoring cadmium and lead emissions discharged to the atmosphere and record
the output of the system according to the provisions of sections (13) and (14)
of this rule.
(d) In place of
mercury testing with EPA Reference Method 29 or as an alternative ASTM
D6784-02, an owner or operator may elect to install, calibrate, maintain, and
operate a continuous emission monitoring system or a continuous automated
sampling system for monitoring mercury emissions discharged to the atmosphere
and record the output of the system according to the provisions of sections
(13) and (14) of this rule, or sections (15) and (16) of this rule, as
appropriate. The owner or operator who elects to continuously monitor mercury
in place of mercury testing with EPA Reference Method 29 or as an alternative
ASTM D6784-02 is not required to complete performance testing for mercury as
specified in paragraph (4)(b)(H) of this rule.
(5) The procedures and test methods specified
in subsections (5)(a) through (l) of this rule must be used for determining
compliance with the sulfur dioxide emission limit under OAR
340-230-0310(4).
(a) EPA Reference Method 19, section 4.3,
must be used to calculate the daily geometric average sulfur dioxide emission
concentration.
(b) EPA Reference
Method 19, section 5.4, must be used to determine the daily geometric average
percent reduction in the potential sulfur dioxide emission
concentration.
(c) The owner or
operator of an affected facility may request that compliance with the sulfur
dioxide emission limit be determined using carbon dioxide measurements
corrected to an equivalent of 7 percent oxygen. The relationship between oxygen
and carbon dioxide levels for the affected facility must be established as
specified in subsection (2)(e) of this rule.
(d) Compliance with the sulfur dioxide
emission limit (concentration or percent reduction) must be determined by using
the continuous emission monitoring system specified in subsection (5)(e) of
this rule to measure sulfur dioxide and calculating 24-hour daily geometric
average emission concentration or a 24-hour daily geometric average percent
reduction using EPA reference Method 19, sections 4.3 and 5.4, as
applicable.
(e) The owner or
operator of an affected facility must install, evaluate, calibrate, maintain,
and operate a continuous emission monitoring system for measuring sulfur
dioxide emissions discharged to the atmosphere and record the output of the
system in accordance with
40 CFR
60.13.
(f) Compliance with the sulfur dioxide
emission limit must be determined based on the 24-hour daily geometric average
of the hourly arithmetic average emission concentrations using continuous
emission monitoring system outlet data if compliance is based on an emission
concentration, or continuous emission monitoring system inlet and outlet data
if compliance is based on a percent reduction.
(g) At a minimum, valid continuous monitoring
system hourly averages must be obtained as specified in paragraphs (5)(g)(A)
and (B) of this rule for 90 percent of the operating hours per calendar quarter
and 95 percent of the operating hours per calendar year that the affected
facility is combusting municipal solid waste.
(A) At least two data points per hour must be
used to calculate each 1-hour arithmetic average.
(B) Each sulfur dioxide 1-hour arithmetic
average must be corrected to 7 percent oxygen on an hourly basis using the
1-hour arithmetic average of the oxygen (or carbon dioxide) continuous emission
monitoring system data.
(h) The 1-hour arithmetic averages required
under subsection (5)(f) of this rule must be expressed in parts per million
corrected to 7 percent oxygen (dry basis) and used to calculate the 24-hour
daily geometric average emission concentrations and daily geometric average
emission percent reductions. The 1-hour arithmetic averages must be calculated
using the data points required under
40 CFR
60.13(e)(2).
(i) All valid continuous emission monitoring
system data must be used in calculating average emission concentrations and
percent reductions even if the minimum continuous emission monitoring system
data requirements of subsection (5)(g) of this rule are not met.
(j) The continuous emission monitoring system
must be operated according to Performance Specification 2 in appendix B of 40
CFR
60 . For sources that have actual inlet emissions less than 100 parts per
million dry volume, the relative accuracy criterion for inlet sulfur dioxide
continuous emission monitoring systems should be no greater than 20 percent of
the mean value of the reference method test data in terms of the units of the
emission standard, or 5 parts per million dry volume absolute value of the mean
difference between the reference method and the continuous emission monitoring
systems, whichever is greater.
(A) During
each relative accuracy test run of the continuous emission monitoring system
required by Performance Specification 2 in appendix B of 40 CFR
60, sulfur
dioxide and oxygen (or carbon dioxide) must be collected concurrently (or
within a 30- to 60-minute period) by both the continuous emission monitors and
the test methods specified in subparagraphs (5)(j)(A)(i) and (ii) of this rule.
(i) For sulfur dioxide, EPA Reference Method
6, 6A, or 6C, or as an alternative ASME PTC-19-10-1981-Part 10, must be
used.
(ii) For oxygen (or carbon
dioxide), EPA Reference Method 3, 3A, or 3B, or as an alternative ASME
PTC-19-10-1981-Part 10, must be used.
(B) The span value of the continuous
emissions monitoring system at the inlet to the sulfur dioxide control device
must be 125 percent of the maximum estimated hourly potential sulfur dioxide
emissions of the municipal waste combustor unit. The span value of the
continuous emission monitoring system at the outlet of the sulfur dioxide
control device must be 50 percent of the maximum estimated hourly potential
sulfur dioxide emissions of the municipal waste combustor unit.
(k) Quarterly accuracy
determinations and daily calibration tests must be performed in accordance with
Procedure 1 in Appendix F of 40 CFR
60.
(l) When sulfur dioxide emissions data are
not obtained because of continuous emission monitoring system breakdowns,
repairs, calibration checks, and/or zero and span adjustments, emissions data
must be obtained by using other monitoring systems as approved by the
Department or EPA Reference Method 19 to provide, as necessary, valid emissions
data for a minimum of 90 percent of the hours per calendar quarter and 95
percent of the hours per calendar year that the affected facility is operated
and combusting municipal solid waste.
(6) The procedures and test methods specified
in subsections (6)(a) through (h) if this rule must be used for determining
compliance with the hydrogen chloride emission limit under OAR
340-230-0310(5).
(a) EPA Reference Method 26 or 26A, as
applicable, must be used to determine the hydrogen chloride emission
concentration. The minimum sampling time for must be 1 hour.
(b) An oxygen (or carbon dioxide) measurement
must be obtained simultaneously with each test run for hydrogen chloride
required by subsection (6)(a) of this rule.
(c) The percent reduction in potential
hydrogen chloride emissions (% PHCl) is computed using equation 2: [Equation
not included. See ED. NOTE.]
(d)
The owner or operator of an affected facility may request that compliance with
the hydrogen chloride emission limit be determined using carbon dioxide
measurements corrected to an equivalent of 7 percent oxygen. The relationship
between oxygen and carbon dioxide levels for the affected facility must be
established as specified in subsection (2)(e) of this rule.
(e) As specified under
40 CFR
60.8,
all performance tests must consist of three test runs. The average of the
hydrogen chloride emission concentrations from the three test runs is used to
determine compliance.
(f) The owner
or operator of an affected facility must conduct a performance test for
hydrogen chloride emissions on a calendar year basis (no less than 9 calendar
months and no more than 15 calendar months following the previous performance
test; and must complete five performance tests in each 5-year calendar
period).
(g) In place of hydrogen
chloride testing with EPA Reference Method 26 or 26A, an owner or operator may
elect to install, calibrate, maintain, and operate a continuous emission
monitoring system for monitoring hydrogen chloride emissions discharged to the
atmosphere and record the output of the system according to the provisions of
sections (13) and (14) of this rule.
(7) The procedures and test methods specified
in subsections (7)(a) through (h) of this rule must be used to determine
compliance with the limits for dioxin/furan emissions under OAR
340-230-0310(6).
(a) EPA Reference Method 1 must be used for
determining the location and number of sampling points.
(b) EPA Reference Method 3, 3A, or 3B, or as
an alternative ASME PTC-19-10-1981-Part 10, as applicable, must be used for
flue gas analysis.
(c) EPA
Reference Method 23 must be used for determining the dioxin/furan emission
concentration.
(A) The minimum sample time
must be 4 hours per test run.
(B)
An oxygen (or carbon dioxide) measurement must be obtained simultaneously with
each EPA Reference Method 23 test run for dioxins/furans.
(d) The owner or operator of an affected
facility must conduct performance tests for dioxin/furan emissions in
accordance with subsection (7)(c) of this rule, according to one of the
schedules specified in paragraphs (7)(d)(A) through (C) of this rule.
(A) Performance tests must be conducted on a
calendar year basis (no less than 9 calendar months and no more than 15
calendar months following the previous performance test; and must complete five
performance tests in each 5-year calendar period).
(B) For the purpose of evaluating system
performance to establish new operating parameter levels, testing new technology
or control technologies, diagnostic testing, or related activities for the
purpose of improving facility performance or advancing the state-of-the-art for
controlling facility emissions, the owner or operator of an affected facility
that qualifies for the performance testing schedule specified in paragraph
(7)(d)(C) of this rule, may test one unit for dioxin/furan and apply the
dioxin/furan operating parameters to similarly designed and equipped units on
site by meeting the requirements specified in subparagraphs (7)(d)(B)(i)
through (iv) of this rule.
(i) Follow the
testing schedule established in paragraph (7)(d)(C) of this rule. For example,
each year a different affected facility at the municipal waste combustor plant
must be tested, and the affected facilities at the plant must be tested in
sequence (e.g., unit 1, unit 2, unit 3, as applicable).
(ii) Where such units use carbon to meet the
applicable dioxin/furan emission limit, upon meeting the requirements in
paragraph (7)(d)(C) of this rule for one affected facility, the owner or
operator may elect to apply the average carbon mass feed rate and associated
carbon injection system operating parameter levels for dioxin/furan as
established in section (13) of this rule to similarly designed and equipped
units on site.
(iii) Upon testing
each subsequent unit in accordance with the testing schedule established in
paragraph (7)(d)(C) of this rule, the dioxin/furan and mercury emissions of the
subsequent unit must not exceed the dioxin/furan and mercury emissions measured
in the most recent test of that unit prior to the revised operating parameter
levels.
(iv) The owner or operator
of an affected facility that selects to follow the performance testing schedule
specified in paragraph (7)(d)(C) of this rule and apply the carbon injection
system operating parameters to similarly designed and equipped units on site
must follow the procedures specified in OAR
340-230-0350(3)(d)
for reporting.
(C) Where
all performance tests over a 2-year period indicate that dioxin/furan emissions
are less than or equal to 7 nanograms per dry standard cubic meter (total mass)
for all affected facilities located within a municipal waste combustor plant,
the owner or operator of the municipal waste combustor plant may elect to
conduct annual performance tests for one affected facility (i.e., unit) per
year at the municipal waste combustor plant. At a minimum, a performance test
for dioxin/furan emissions must be conducted on a calendar year basis (no less
than 9 calendar months and no more than 15 months following the previous
performance test; and must complete five performance tests in each 5-year
calendar period) for one affected facility at the municipal waste combustor
plant. Each year a different affected facility at the municipal waste combustor
plant must be tested, and the affected facilities at the plant must be tested
in sequence (e.g., unit 1, unit 2, unit 3, as applicable). If each annual
performance test continues to indicate a dioxin/furan emission level less than
or equal to 7 nanograms per dry standard cubic meter (total mass), the owner or
operator may continue conducting a performance test on only one affected
facility per year. If any annual performance test indicates either a
dioxin/furan emission level greater than 7 nanograms per dry standard cubic
meter (total mass), performance tests thereafter must be conducted annually on
all affected facilities at the plant until and unless all annual performance
tests for all affected facilities at the plant over a 2-year period indicate a
dioxin/furan emission level less than or equal to 7 nanograms per dry standard
cubic meter (total mass).
(e) The owner or operator of an affected
facility that selects to follow the performance testing schedule specified in
paragraph (7)(d)(C) of this rule must follow the procedures specified in OAR
340-230-0350(3)(d)
for reporting the selection of this schedule.
(f) The owner or operator of an affected
facility where activated carbon is used must follow the procedures specified in
section (12) of this rule for measuring and calculating the carbon usage
rate.
(g) The owner or operator of
an affected facility may request that compliance with the dioxin/furan emission
limit be determined using carbon dioxide measurements corrected to an
equivalent of 7 percent oxygen. The relationship between oxygen and carbon
dioxide levels for the affected facility must be established as specified in
subsection (2)(e) of this rule.
(h)
As specified under
40 CFR
60.8,
all performance tests must consist of three test runs. The average of the
dioxin/furan emission concentrations from the three test runs is used to
determine compliance.
(i) In place
of dioxin/furan sampling and testing with EPA Reference Method 23, an owner or
operator may elect to sample dioxin/furan by installing, calibrating,
maintaining, and operating a continuous automated sampling system for
monitoring dioxin/furan emissions discharged to the atmosphere, recording the
output of the system, and analyzing the sample using EPA Reference Method 23.
This option to use a continuous automated sampling system takes effect on the
date a final performance specification applicable to dioxin/furan from monitors
is published in the Federal Register or the date of approval of a site-specific
monitoring plan. The owner or operator of an affected facility who elects to
continuously sample dioxin/furan emissions instead of sampling and testing
using EPA Reference Method 23 must install, calibrate, maintain, and operate a
continuous automated sampling system and must comply with the requirements
specified in sections (15) and (16) of this rule.
(8) The procedures and test methods specified
in subsections (8)(a) through (i) of this rule must be used to determine
compliance with the nitrogen oxides emission limit for affected facilities.
(a) Compliance with the nitrogen oxides
emission limit must be determined by using the continuous emission monitoring
system specified in subsection (8)(c) of this rule for measuring nitrogen
oxides and calculating a 24-hour daily arithmetic average emission
concentration using EPA Reference Method 19, section 4.1.
(b) An owner or operator may request that
compliance with the nitrogen oxides emission limit be determined using carbon
dioxide measurements corrected to an equivalent of 7 percent oxygen. The
relationship between oxygen and carbon dioxide levels for the affected facility
must be established as specified in subsection (2)(e) of this rule.
(c) The owner or operator of an affected
facility must install, calibrate, maintain, and operate a continuous emission
monitoring system for measuring nitrogen oxides discharged to the atmosphere,
and record the output of the system.
(d) At a minimum, valid continuous emission
monitoring system hourly averages must be obtained as specified in paragraphs
(8)(d)(A) and (B) of this rule for 90 percent of the operating hours per
calendar quarter and for 95 percent of the operating hours per calendar year
that the affected facility is combusting municipal solid waste.
(A) At least 2 data points per hour must be
used to calculate each 1-hour arithmetic average.
(B) Each nitrogen oxides 1-hour arithmetic
average must be corrected to 7 percent oxygen on an hourly basis using the
1-hour arithmetic average of the oxygen (or carbon dioxide) continuous emission
monitoring system data.
(e) The 1-hour arithmetic averages must be
expressed in parts per million by volume (dry basis) and used to calculate the
24-hour daily arithmetic average concentrations. The 1-hour arithmetic averages
must be calculated using the data points required under
40 CFR
60.13(e)(2).
(f) All valid continuous emission monitoring
system data must be used in calculating emission averages even if the minimum
continuous emission monitoring system data requirements of subsection (8)(d) of
this rule are not met.
(g) The
owner or operator of an affected facility must operate the continuous emission
monitoring system according to Performance Specification 2 in Appendix B of 40
CFR
60 and must follow the procedures and methods specified in paragraphs
(8)(g)(A) and (B) of this rule.
(A) During
each relative accuracy test run of the continuous emission monitoring system
required by Performance Specification 2 in Appendix B of 40 CFR
60, nitrogen
oxides and oxygen (or carbon dioxide) must be collected concurrently (or within
a 30- to 60-minute period) by both the continuous emission monitors and the
test methods specified in subparagraphs (8)(g)(A)(i) and (ii) of this rule.
(i) For nitrogen oxides, EPA Reference
Methods 7, 7A, 7C, 7D, or 7E must be used.
(ii) For oxygen (or carbon dioxide), EPA
Reference Method 3, 3A, or 3B, or as an alternative ASME PTC-19-10-1981-Part
10, as applicable, must be used.
(B) The span value of the continuous emission
monitoring system must be 125 percent of the maximum estimated hourly potential
nitrogen oxide emissions of the municipal waste combustor unit.
(h) Quarterly accuracy
determinations and daily calibration drift tests must be performed in
accordance with Procedure 1 in Appendix F of 40 CFR Part
60.
(i) When nitrogen oxides continuous emissions
data are not obtained because of continuous emission monitoring system
breakdowns, repairs, calibration checks, and zero and span adjustments,
emissions data must be obtained using other monitoring systems as approved by
the Department or EPA Reference Method 19 to provide, as necessary, valid
emissions data for a minimum of 90 percent of the hours per calendar quarter
and 95 percent of the hours per calendar year the unit is operated and
combusting municipal solid waste.
(9) The procedures specified in subsections
(9)(a) through (k) of this rule must be used for determining compliance with
the operating requirements under OAR
340-230-0320.
(a) Compliance with the carbon monoxide
emission limits in OAR
340-230-0320(1)
must be determined using a 4-hour block arithmetic average.
(b) The owner or operator of an affected
facility must install, calibrate, maintain, and operate a continuous emission
monitoring system for measuring carbon monoxide at the combustor outlet and
record the output of the system and must follow the procedures and methods
specified in paragraphs (9)(a)(A) through (C) of this rule:
(A) The continuous emission monitoring system
must be operated according to Performance Specification 4A in Appendix B of 40
CFR
60.
(B) During each relative
accuracy test run of the continuous emission monitoring system required by
Performance Specification 4A in Appendix B of 40 CFR Part
60, carbon monoxide
and oxygen (or carbon dioxide) data must be collected concurrently (or within a
30- to 60-minute period) by both the continuous emission monitors and the test
methods specified in subparagraphs (9)(b)(B)(i) and (ii) of this rule. For
affected facilities subject to the 100 parts per million dry volume carbon
monoxide standard, the relative accuracy criterion of 5 parts per million dry
volume is calculated as the absolute value of the mean difference between the
reference method and continuous emission monitoring systems.
(i) For carbon monoxide, EPA Reference
Methods 10, 10A, or 10B must be used.
(ii) For oxygen (or carbon dioxide), EPA
Reference Method 3, 3A, or 3B, or ASME PTC-19-10-1981--Part 10 (incorporated by
reference, see
40 CFR
60.17), as applicable, must be
used.
(C) The span value
of the continuous emission monitoring system must be 125 percent of the maximum
estimated hourly potential carbon monoxide emissions of the municipal waste
combustor unit.
(c) The
4-hour block daily arithmetic averages specified in subsection (9)(a) of this
rule must be calculated from 1-hour arithmetic averages expressed in parts per
million by volume corrected to 7 percent oxygen (dry basis). The 1-hour
arithmetic averages must be calculated using the data points generated by the
continuous emission monitoring system. At least two data points must be used to
calculate each 1-hour arithmetic average.
(d) The owner or operator of an affected
facility may request that compliance with the carbon monoxide emission limit be
determined using carbon dioxide measurements corrected to an equivalent of 7
percent oxygen. The relationship between oxygen and carbon dioxide levels for
the affected facility must be established as specified in subsection (2)(e) of
this rule.
(e) The procedures
specified in paragraphs (9)(e)(A) through (D) of this rule must be used to
determine compliance with load level requirements under OAR
340-230-0320(2).
(A) The owner or operator of an affected
facility with steam generation capability must install, calibrate, maintain,
and operate a steam flow meter or a feedwater flow meter; measure steam (or
feedwater) flow in kilograms per hour (or pounds per hour) on a continuous
basis; and record the output of the monitor. Steam (or feedwater) flow must be
calculated in 4-hour block arithmetic averages.
(B) The method included in the "American
Society of Mechanical Engineers Power Test Codes: Test Code for Steam
Generating Units, Power Test Code 4.1-1964 (R1991)" section 4 (incorporated by
reference, see
40 CFR
60.17) must be used for calculating the steam
(or feedwater) flow required under paragraph (9)(c)(A) of this rule. The
recommendations in "American Society of Mechanical Engineers Interim Supplement
19.5 on Instruments and Apparatus: Application, Part II of Fluid Meters, 6th
edition (1971)," chapter 4 (incorporated by reference -- see
40 CFR
60.17) must be followed for design,
construction, installation, calibration, and use of nozzles and orifices except
as specified in paragraph (9)(e)(C) of this rule:
(C) Measurement devices such as flow nozzles
and orifices are not required to be recalibrated after they are
installed.
(D) All signal
conversion elements associated with steam (or feedwater flow) measurements must
be calibrated according to the manufacturer's instructions before each
dioxin/furan performance test, and at least once per year.
(f) To determine compliance with the maximum
particulate matter control device temperature requirements under OAR
340-230-0320(3),
the owner or operator of an affected facility must install, calibrate,
maintain, and operate a device for measuring on a continuous basis the
temperature of the flue gas stream at the inlet to each particulate matter
control device utilized by the affected facility. Temperature must be
calculated in 4-hour block arithmetic averages.
(g) The maximum demonstrated municipal waste
combustor unit load must be determined during the initial performance test for
dioxins/furans and each subsequent performance test during which compliance
with the dioxin/furan emission limit specified in OAR
340-230-0310(6)
is achieved. The maximum demonstrated municipal waste combustor unit load shall
be the highest 4-hour arithmetic average load achieved during four consecutive
hours during the most recent test during which compliance with the dioxin/furan
emission limit was achieved. If a subsequent dioxin/furan performance test is
being performed on only one affected facility at the MWC plant, as provided in
paragraph (7)(d)(C) of this rule, the owner or operator may elect to apply the
same maximum municipal waste combustor unit load from the tested facility for
all the similarly designed and operated affected facilities at the MWC
plant.
(h) For each particulate
matter control device employed at the affected facility, the maximum
demonstrated particulate matter control device temperature must be determined
during each performance test during which compliance with the dioxin/furan
emission limit specified in OAR
340-230-0310(6)
is achieved. The maximum demonstrated particulate matter control device
temperature shall be the highest 4-hour arithmetic average temperature achieved
at the particulate matter control device inlet during four consecutive hours
during the most recent test during which compliance with the dioxin/furan limit
was achieved. If a subsequent dioxin/furan performance test is being performed
on only one affected facility at the MWC plant, as provided in paragraph
(7)(d)(C) of this rule, the owner or operator may elect to apply the same
maximum particulate matter control device temperature from the tested facility
for all the similarly designed and operated affected facilities at the MWC
plant.
(i) At a minimum, valid
continuous emission monitoring system hourly averages must be obtained as
specified in paragraphs (9)(i)(A) and (B) of this rule for at least 90 percent
of the operating hours per calendar quarter and 95 percent of the operating
hours per calendar year that the affected facility is combusting municipal
solid waste.
(A) At least two data points per
hour must be used to calculate each 1-hour arithmetic average.
(B) At a minimum, each carbon monoxide 1-hour
arithmetic must be corrected to 7-percent oxygen on an hourly basis using the
1-hour arithmetic average of the oxygen (or carbon dioxide) continuous emission
monitoring system data.
(j) All valid continuous emission monitoring
system data must be used in calculating the parameters specified under section
(9) of this rule even if the minimum data requirements of subsection (9)(i) of
this rule are not met. When carbon monoxide continuous emission data are not
obtained because of continuous emission monitoring system breakdowns, repairs,
calibration checks, and zero and span adjustments, emissions data must be
obtained using other monitoring systems as approved by the Department or EPA
Reference Method 10 to provide, as necessary, the minimum valid emission
data.
(k) Quarterly accuracy
determinations and daily calibration drift tests for the carbon monoxide
continuous emission monitoring system must be performed in accordance with
Procedure 1 in appendix F of 40 CFR part
60.
(10) The procedures specified in subsections
(10)(a) an (b) of this rule must be used for calculating municipal waste
combustor unit capacity as defined by
40
CFR
60.51b.
(a) For municipal waste combustor units
capable of combusting municipal solid waste continuously for a 24-hour period,
municipal waste combustor unit capacity must be calculated based on 24 hours of
operation at the maximum charging rate. The maximum charging rate must be
determined as specified in paragraphs (10)(a)(A) and (B) of this rule, as
applicable:
(A) For combustors that are
designed based on heat capacity, the maximum charging rate must be calculated
based on the maximum design heat input capacity of the unit and a heating value
of 12,800 kilojoules per kilogram for combustors firing refuse-derived fuel and
a heating value of 10,500 kilojoules per kilogram for combustors firing
municipal solid waste that is not refuse-derived fuel.
(B) For combustors that are not designed
based on heat capacity, the maximum charging rate shall be the maximum design
charging rate.
(b) For
batch feed municipal waste combustor units, municipal waste combustor unit
capacity must be calculated as the maximum design amount of municipal solid
waste that can be charged per batch multiplied by the maximum number of batches
that could be processed in a 24-hour period. The maximum number of batches that
could be processed in a 24-hour period is calculated as 24 hours divided by the
design number of hours required to process one batch of municipal solid waste,
and may include fractional batches (e.g., if one batch requires 16 hours, then
24/16, or 1.5 batches, could be combusted in a 24-hour period). For batch
combustors that are designed based on heat capacity, the design heating value
of 12,800 kilojoules per kilogram for combustors firing refuse-derived fuel and
a heating value of 10,500 kilojoules per kilogram for combustors firing
municipal solid waste that is not refuse-derived fuel must be used in
calculating the municipal waste combustor unit capacity in megagrams per day of
municipal solid waste.
(11) The procedures specified in subsections
(11)(a) through (c) of this rule must be used for determining compliance with
the fugitive ash emission limit under OAR
340-0230-0335.
(a) EPA Reference Method 22 must be used for
determining compliance with the fugitive ash emission limit under OAR
340-0230-0335. The minimum observation time must be a series of three 1-hour
observations. The observation period must include times when the facility is
transferring ash from the municipal waste combustor unit to the area where ash
is stored or loaded into containers or trucks.
(b) The average duration of visible emissions
per hour must be calculated from the three 1-hour observations. The average
must be used to determine compliance with OAR
340-0230-0335.
(c) The owner or operator of an affected
facility must conduct a performance test for fugitive ash emissions on a
calendar year basis (no less than 9 calendar months and no more than 15 months
following the previous performance test; and must complete five performance
tests in each 5-year period).
(12) The owner or operator of an affected
facility where activated carbon injection is used to comply with the mercury
emission limit under OAR
340-230-0310(3)(c),
the dioxin/furan emission limits under OAR
340-230-0310(6),
or the dioxin/furan emission level specified in paragraph (7)(d)(C) of this
rule must follow the procedures specified in subsections (12)(a) through (d) of
this rule.
(a) During the performance tests
for dioxins/furans and mercury, as applicable, the owner or operator must
estimate an average carbon mass feed rate based on carbon injection system
operating parameters such as the screw feeder speed, hopper volume, hopper
refill frequency, or other parameters appropriate to the feed system being
employed, as specified in paragraphs (12)(a)(A) and (B) of this rule.
(A) An average carbon mass feed rate in
kilograms per hour or pounds per hour must be estimated during each performance
test for mercury emissions.
(B) An
average carbon mass feed rate in kilograms per hour or pounds per hour must be
estimated during each performance test for dioxin/furan emissions, if
applicable. If a subsequent dioxin/furan performance test is being performed on
only one affected facility at the MWC plant, as provided in paragraph (7)(d)(C)
of this rule, the owner or operator may elect to apply the same estimated
average carbon mass feed rate from the tested facility for all the similarly
designed and operated affected facilities at the MWC plant.
(b) During operation of the
affected facility, the carbon injection system operating parameter(s) that are
the primary indicator(s) of the carbon mass feed rate (e.g., screw feeder
setting) must be averaged over a block 8-hour period, and the 8-hour average
must equal or exceed the level(s) documented during the performance tests
specified under paragraphs (12)(a)(A) and (B) of this rule, except as specified
in paragraphs (12)(b)(A) and (B) of this rule.
(A) During the annual dioxin/furan or mercury
performance test and the 2 weeks preceding the annual dioxin/furan or mercury
performance test, no limit is applicable for average mass carbon feed rate if
the provisions of paragraph (12)(b)(B) of this rule are met.
(B) The limit for average mass carbon feed
rate may be waived in accordance with permission granted by the Administrator
for the purpose of evaluating system performance, testing new technology or
control technologies, diagnostic testing, or related activities for the purpose
of improving facility performance or advancing the state-of-the-art for
controlling facility emissions.
(c) The owner or operator must estimate the
total carbon usage of the plant (kilograms or pounds) for each calendar quarter
by two independent methods, according to the procedures in paragraphs
(12)(c)(A) and (B) of this rule.
(A) The
weight of carbon delivered to the plant.
(B) Estimate the average carbon mass feed
rate in kilograms per hour or pounds per hour for each hour of operation for
each affected facility based on the parameters specified under subsection
(12)(a) of this rule, and sum the results for all affected facilities at the
plant for the total number of hours of operation during the calendar
quarter.
(d) Pneumatic
injection pressure or other carbon injection system operational indicator must
be used to provide additional verification of proper carbon injection system
operation. The operational indicator must provide an instantaneous visual
and/or audible alarm to alert the operator of a potential interruption in the
carbon feed that would not normally be indicated by direct monitoring of carbon
mass feed rate (e.g., continuous weight loss feeder) or monitoring of the
carbon system operating parameter(s) that are the indicator(s) of carbon mass
feed rate (e.g., screw feeder speed). The carbon injection system operational
indicator used to provide additional verification of carbon injection system
operation, including basis for selecting the indicator and operator response to
the indicator alarm, must be included in subsection (5)(f) of this rule of the
site-specific operating manual required under OAR
340-230-0330(4).
(13) In place of periodic manual
testing of mercury, cadmium, lead, or hydrogen chloride with EPA Reference
Method 26, 26A, 29, or as an alternative ASTM D6784-02 (as applicable),
affected facilities may elect to install, calibrate, maintain, and operate a
continuous emission monitoring system for monitoring emissions discharged to
the atmosphere and record the output of the system. The option to use a
continuous emission monitoring system for mercury takes effect on the date of
approval of the site-specific monitoring plan required in subsection (13)(m) of
this rule and section (14) of this rule. The option to use a continuous
emission monitoring system for cadmium, lead, or hydrogen chloride takes effect
on the date a final performance specification applicable to cadmium, lead, or
hydrogen chloride monitor is published in the Federal Register or the date of
approval of the site-specific monitoring plan required in subsection (13)(m) of
this rule and section (14) of this rule. The owner or operator of an affected
facility who elects to continuously monitor emissions instead of conducting
manual performance testing must install, calibrate, maintain, and operate a
continuous emission monitoring system and must comply with the requirements in
subsections (13)(a) through (n) of this rule.
(a) Notify the Administrator and the
Department one month before starting use of the system.
(b) Notify the Administrator and the
Department one month before stopping use of the system.
(c) The monitor must be installed, evaluated,
and operated in accordance with
40 CFR
60.13.
(d) The initial performance evaluation must
be completed no later than 180 days after the date of initial startup of the
affected facility, as specified under
40 CFR
60.8 or
within 180 days of notification to the Administrator and the Department of use
of the continuous monitoring system if the owner or operator was previously
determining compliance by EPA Reference Method 26, 26A, 29, or as an
alternative ASTM D6784-02 (as applicable) performance tests, whichever is
later.
(e) The owner or operator
may request that compliance with the emission limits be determined using carbon
dioxide measurements corrected to an equivalent of 7 percent oxygen. The
relationship between oxygen and carbon dioxide levels for the affected facility
must be established as specified in subsection (2)(e) of this rule.
(f) The owner or operator must conduct an
initial performance test for emissions as required under
40 CFR
60.8.
Compliance with the emission limits must be determined by using the continuous
emission monitoring system specified in section (13) of this rule to measure
emissions and calculating a 24-hour block arithmetic average emission
concentration using EPA Reference Method 19, section 12.4.1.
(g) Compliance with the emission limits must
be determined based on the 24-hour daily (block) average of the hourly
arithmetic average emission concentrations using continuous emission monitoring
system outlet data.
(h) Beginning
on April 28, 2008 for mercury and on the date two years after final performance
specifications for cadmium, lead or hydrogen chloride monitors are published in
the Federal Register or the date two years after approval of a site-specific
monitoring plan, valid continuous monitoring system hourly averages must be
obtained as specified in paragraphs (13)(h)(A) and (B) of this rule for at
least 90 percent of the operating hours per calendar quarter and 95 percent of
the operating hours per calendar year that the affected facility is combusting
municipal solid waste.
(A) At least two data
points per hour must be used to calculate each 1-hour arithmetic
average.
(B) Each 1-hour arithmetic
average must be corrected to 7 percent oxygen on an hourly basis using the
1-hour arithmetic average of the oxygen (or carbon dioxide) continuous emission
monitoring system data.
(i) The 1-hour arithmetic averages required
under subsection (13)(g) of this rule must be expressed in micrograms per dry
standard cubic meter for mercury, cadmium, lead and parts per million dry
volume for hydrogen chloride corrected to 7 percent oxygen (dry basis) and must
be used to calculate the 24-hour daily arithmetic (block) average emission
concentrations. The 1-hour arithmetic averages must be calculated using the
data points required under
40 CFR
60.13(e)(2).
(j) All valid continuous emission monitoring
system data must be used in calculating average emission concentrations even if
the minimum continuous emission monitoring system data requirements of
subsection (13)(h) of this rule are not met.
(k) The continuous emission monitoring system
for mercury must be operated according to Performance Specification 12A in 40
CFR part
60 appendix B or the approved site-specific monitoring plan.
(l) During each relative accuracy test run of
the continuous emission monitoring system required by the performance
specifications in subsection (13)(k) of this rule, mercury, cadmium, lead,
hydrogen chloride, and oxygen (or carbon dioxide) data must be collected
concurrently (or within a 30- to 60-minute period) by both the continuous
emission monitors and the test methods specified in paragraphs (13)(l)(A)
through (C) of this rule.
(A) For mercury,
cadmium, and lead, EPA Reference Method 29 or as an alternative ASTM D6784-02
must be used.
(B) For hydrogen
chloride, EPA Reference Method 26 or 26A must be used.
(C) For oxygen (or carbon dioxide), EPA
Reference Method 3, 3A, or 3B, as applicable must be used.
(m) The owner or operator who elects to
install, calibrate, maintain, and operate a continuous emission monitoring
system for mercury, cadmium, lead, or hydrogen chloride must develop and
implement a site-specific monitoring plan as specified in section (14) of this
rule. The owner or operator who relies on a performance specification may refer
to that document in addressing applicable procedures and criteria.
(n) When emissions data are not obtained
because of continuous emission monitoring system breakdowns, repairs,
calibration checks, and zero and span adjustments, parametric monitoring data
must be obtained by using other monitoring systems as approved by
EPA.
(14) The owner or
operator who elects to install, calibrate, maintain, and operate a continuous
emission monitoring system for mercury, cadmium, lead, or hydrogen chloride
must develop and submit for approval by EPA, a site-specific mercury, cadmium,
lead, or hydrogen chloride monitoring plan that addresses the elements and
requirements in subsections (14)(a) through (g) of this rule.
(a) Installation of the continuous emission
monitoring system sampling probe or other interface at a measurement location
relative to each affected process unit such that the measurement is
representative of control of the exhaust emissions (e.g., on or downstream of
the last control device).
(b)
Performance and equipment specifications for the sample interface, the
pollutant concentration analyzer, and the data collection and reduction
system.
(c) Performance evaluation
procedures and acceptance criteria (e.g., calibrations).
(d) Provisions for periods when the
continuous emission monitoring system is out of control as described in
paragraphs (14)(d)(A) through (C) of this rule.
(A) A continuous emission monitoring system
is out of control if either of the conditions in subparagraph (14)(d)(A)(i) or
(ii) of this rule are met.
(i) The zero
(low-level), mid-level (if applicable), or high-level calibration drift exceeds
two times the applicable calibration drift specification in the applicable
performance specification or in the relevant standard; or
(ii) The continuous emission monitoring
system fails a performance test audit (e.g., cylinder gas audit), relative
accuracy audit, relative accuracy test audit, or linearity test
audit.
(B) When the
continuous emission monitoring system is out of control as defined in paragraph
(14)(d)(A) of this rule, the owner or operator of the affected source must take
the necessary corrective action and must repeat all necessary tests that
indicate that the system is out of control. The owner or operator must take
corrective action and conduct retesting until the performance requirements are
below the applicable limits. The beginning of the out-of-control period is the
hour the owner or operator conducts a performance check (e.g., calibration
drift) that indicates an exceedance of the performance requirements established
under this part. The end of the out-of-control period is the hour following the
completion of corrective action and successful demonstration that the system is
within the allowable limits. During the period the continuous emission
monitoring system is out of control, recorded data shall not be used in data
averages and calculations or to meet any data availability requirements in
subsection (13)(h) of this rule.
(C) The owner or operator of a continuous
emission monitoring system that is out of control as defined in subsection
(14)(d) of this rule must submit all information concerning out-of-control
periods, including start and end dates and hours and descriptions of corrective
actions taken in the annual or semiannual compliance reports required in OAR
340-230-0350(3) or
(4).
(e) Ongoing data quality assurance procedures
for continuous emission monitoring systems as described in paragraphs
(14)(e)(A) and (B) of this rule.
(A) Develop
and implement a continuous emission monitoring system quality control program.
As part of the quality control program, the owner or operator must develop and
submit to EPA for approval, upon request, a site-specific performance
evaluation test plan for the continuous emission monitoring system performance
evaluation required in paragraph (14)(e)(B) of this rule. In addition, each
quality control program must include, at a minimum, a written protocol that
describes procedures for each of the operations described in subparagraphs
(14)(e)(A)(i) through (vi) of this rule.
(i)
Initial and any subsequent calibration of the continuous emission monitoring
system;
(ii) Determination and
adjustment of the calibration drift of the continuous emission monitoring
system;
(iii) Preventive
maintenance of the continuous emission monitoring system, including spare parts
inventory;
(iv) Data recording,
calculations, and reporting;
(v)
Accuracy audit procedures, including sampling and analysis methods;
and
(vi) Program of corrective
action for a malfunctioning continuous emission monitoring system.
(B) The performance evaluation
test plan must include the evaluation program objectives, an evaluation program
summary, the performance evaluation schedule, data quality objectives, and both
an internal and external quality assurance program. Data quality objectives are
the pre-evaluation expectations of precision, accuracy, and completeness of
data. The internal quality assurance program must include, at a minimum, the
activities planned by routine operators and analysts to provide an assessment
of continuous emission monitoring system performance, for example, plans for
relative accuracy testing using the appropriate reference method. The external
quality assurance program must include, at a minimum, systems audits that
include the opportunity for on-site evaluation by the Administrator or the
Department of instrument calibration, data validation, sample logging, and
documentation of quality control data and field maintenance
activities.
(f) Conduct
a performance evaluation of each continuous emission monitoring system in
accordance with the site-specific monitoring plan.
(g) Operate and maintain the continuous
emission monitoring system in continuous operation according to the
site-specific monitoring plan.
(15) In place of periodic manual testing of
dioxin/furan or mercury with EPA Reference Method 23, 29, or as an alternative
ASTM D6784-02 (as applicable), the owner or operator of an affected facility
may elect to install, calibrate, maintain, and operate a continuous automated
sampling system for determining emissions discharged to the atmosphere. This
option takes effect on the date a final performance specification applicable to
such continuous automated sampling systems is published in the Federal Register
or the date of approval of a site-specific monitoring plan. The owner or
operator of an affected facility who elects to use a continuous automated
sampling system to determine emissions instead of conducting manual performance
testing must install, calibrate, maintain, and operate the sampling system and
conduct analyses in compliance with the requirements specified in subsections
(15)(a) through (k) of this rule.
(a) Notify
the Administrator and the Department one month before starting use of the
system.
(b) Notify the
Administrator and the Department one month before stopping use of the
system.
(c) The initial performance
evaluation must be completed within 180 days of notification to the
Administrator and the Department of use of the continuous monitoring system if
the owner or operator was previously determining compliance by manual
performance testing using Method 23, 29, or as an alternative ASTM D6784-02 (as
applicable), whichever is later.
(d) The owner or operator may request that
compliance with the emission limits be determined using carbon dioxide
measurements corrected to an equivalent of 7 percent oxygen. The relationship
between oxygen and carbon dioxide levels for the affected facility must be
established as specified in subsection (2)(e) of this rule.
(e) The owner or operator must conduct an
initial performance test for emissions as required under
40 CFR
60.8.
Compliance with the emission limits must be determined by using the continuous
automated sampling system specified in section (15) of this rule to collect
integrated samples and analyze emissions for the time period specified in
paragraphs (15)(e)(A) and (B) of this rule.
(A) For dioxin/furan, the continuous
automated sampling system must collect an integrated sample over each 2-week
period. The collected sample must be analyzed using EPA Reference Method
23.
(B) For mercury, the continuous
automated sampling system must collect an integrated sample over each 24-hour
daily period and the sample must be analyzed according to the applicable final
performance specification or the approved site-specific monitoring plan
required by section (16) of this rule.
(f) Compliance with the emission limits must
be determined based on 2-week emission concentrations for dioxin/furan and on
the 24-hour daily emission concentrations for mercury using samples collected
at the system outlet. The emission concentrations must be expressed in
nanograms per dry standard cubic meter (total mass) for dioxin/furan and
micrograms per dry standard cubic meter for mercury, corrected to 7 percent
oxygen (dry basis).
(g) Beginning
on the date two years after the respective final performance specification for
continuous automated sampling systems for dioxin/furan or mercury is published
in the Federal Register or two years after approval of a site-specific
monitoring plan, the continuous automated sampling system must be operated and
collect emissions for at least 90 percent of the operating hours per calendar
quarter and 95 percent of the operating hours per calendar year that the
affected facility is combusting municipal solid waste.
(h) All valid data must be used in
calculating emission concentrations.
(i) The continuous automated sampling system
must be operated according to the final performance specification or the
approved site-specific monitoring plan.
(j) The owner or operator who elects to
install, calibrate, maintain, and operate a continuous automated sampling
system for dioxin/furan or mercury must develop and implement a site-specific
monitoring plan as specified in section (16) of this rule. The owner or
operator who relies on a performance specification may refer to that document
in addressing applicable procedures and criteria.
(k) When emissions data are not obtained
because of continuous automated sampling system breakdowns, repairs, quality
assurance checks, or adjustments, parametric monitoring data must be obtained
by using other monitoring systems as approved by EPA.
(16) The owner or operator who elects to
install, calibrate, maintain, and operate a continuous automated sampling
system for dioxin/furan or mercury must develop and submit for approval by EPA,
a site-specific monitoring plan that has sufficient detail to assure the
validity of the continuous automated sampling system data and that addresses
the elements and requirements in subsections (16)(a) through (g) of this rule.
(a) Installation of the continuous automated
sampling system sampling probe or other interface at a measurement location
relative to each affected process unit such that the measurement is
representative of control of the exhaust emissions (e.g., on or downstream of
the last control device).
(b)
Performance and equipment specifications for the sample interface, the
pollutant concentration analytical method, and the data collection
system.
(c) Performance evaluation
procedures and acceptance criteria.
(d) Provisions for periods when the
continuous automated sampling system is malfunctioning or is out of control as
described in paragraphs (16)(d)(A) through (C) of this rule.
(A) The site-specific monitoring plan must
identify criteria for determining that the continuous automated sampling system
is out of control. This includes periods when the sampling system is not
collecting a representative sample or is malfunctioning, or when the analytical
method does not meet site-specific quality criteria established in subsection
(16)(e) of this rule.
(B) When the
continuous automated sampling system is out of control as defined in paragraph
(16)(d)(A) of this rule, the owner or operator must take the necessary
corrective action and must repeat all necessary tests that indicate that the
system is out of control. The owner or operator must take corrective action and
conduct retesting until the performance requirements are within the applicable
limits. The out-of-control period includes all hours that the sampling system
was not collecting a representative sample or was malfunctioning, or hours
represented by a sample for which the analysis did not meet the relevant
quality criteria. Emissions data obtained during an out-of-control period shall
not be used in determining compliance with the emission limits or to meet any
data availability requirements in subsection (15)(h) of this rule.
(C) The owner or operator of a continuous
automated sampling system that is out of control as defined in subsection
(16)(d) of this rule must submit all information concerning out-of-control
periods, including start and end dates and hours and descriptions of corrective
actions taken in the annual or semiannual compliance reports required in OAR
340-230-0350(3) or
(4).
(e) Ongoing data quality assurance procedures
for continuous automated sampling systems as described in paragraphs (16)(e)(A)
and (B) of this rule.
(A) Develop and
implement a continuous automated sampling system and analysis quality control
program. As part of the quality control program, affected facilities must
develop and submit to EPA for approval, upon request, a site-specific
performance evaluation test plan for the continuous automated sampling system
performance evaluation required in paragraph (16)(e)(B) of this rule. In
addition, each quality control program must include, at a minimum, a written
protocol that describes procedures for each of the operations described in
subparagraphs (16)(e)(A)(i) through (vii) of this rule.
(i) Correct placement, installation of the
continuous automated sampling system such that the system is collecting a
representative sample of gas;
(ii)
Initial and subsequent calibration of flow such that the sample collection rate
of the continuous automated sampling system is known and verifiable;
(iii) Procedures to assure representative
(e.g., proportional or isokinetic) sampling;
(iv) Preventive maintenance of the continuous
automated sampling system, including spare parts inventory and procedures for
cleaning equipment, replacing sample collection media, or other servicing at
the end of each sample collection period;
(v) Data recording and reporting, including
an automated indicator and recording device to show when the continuous
automated monitoring system is operating and collecting data and when it is not
collecting data;
(vi) Accuracy
audit procedures for analytical methods; and
(vii) Program of corrective action for a
malfunctioning continuous automated sampling system.
(B) The performance evaluation test plan must
include the evaluation program objectives, an evaluation program summary, the
performance evaluation schedule, data quality objectives, and both an internal
and external quality assurance program. Data quality objectives are the
pre-evaluation expectations of precision, accuracy, and completeness of data.
The internal quality assurance program must include, at a minimum, the
activities planned by routine operators and analysts to provide an assessment
of continuous automated sampling system performance, for example, plans for
relative accuracy testing using the appropriate reference method in subsection
(15)(c) of this rule, and an assessment of quality of analysis results. The
external quality assurance program must include, at a minimum, systems audits
that include the opportunity for on-site evaluation by the Administrator or the
Department of instrument calibration, data validation, sample logging, and
documentation of quality control data and field maintenance
activities.
(f) Conduct
a performance evaluation of each continuous automated sampling system in
accordance with the site-specific monitoring plan.
(g) Operate and maintain the continuous
automated sampling system in continuous operation according to the
site-specific monitoring plan.
(17) Continuous monitoring for opacity,
sulfur dioxide, nitrogen oxides, carbon monoxide, and diluent gases (oxygen or
carbon dioxide) must be conducted in accordance with the Department's
Continuous Monitoring Manual and the specific requirements of this rule. If at
any time there is a conflict between the Department's Continuous Monitoring
Manual and the federal requirements contained in
40 CFR
60.13, Appendix B and Appendix F), the
federal requirements must govern. [NOTE: The Department's Continuous Monitoring
Manual is published at OAR
340-200-0035.]
[NOTE: View a PDF of equations, EPA Performance Specifications,
and EPA Procedures by clicking on "Tables" link below.]
[NOTE: View a PDF of referenced EPA Methods by clicking on
"Tables" link following OAR
340-230-8010.]