Or. Admin. Code § 340-240-0540 - Compliance Schedule for Existing Industrial Sources
(1) Except as provided in sections (2) and
(3) of this rule, compliance with applicable requirements of OAR
340-240-0500 through
340-240-0540 for a source that
is built and located in the Klamath Falls Nonattainment Area prior to December
14, 2012 must be demonstrated by the owner or operator of the source as
expeditiously as possible, but in no case later than the following schedule:
(a) No later than June 15, 2013, the owner or
operator must submit Design Criteria and a Notice of Intent to Construct for
emission-control systems for complying with OAR
340-240-0510 through
340-240-0540 for DEQ review and
approval; If the DEQ disapproves the Design Criteria, the owner or operator
must revise the Design Criteria to meet the DEQ's objections and submit the
revised Design Criteria to the DEQ no later than one month after receiving the
DEQ's disapproval;
(b) No later
than three months after receiving the DEQ's approval of the Design Criteria,
the owner or operator must submit to the DEQ copies of purchase orders for any
emission-control devices;
(c) No
later than eight months after receiving the DEQ's approval of the Design
Criteria, the owner or operator must submit to the DEQ vendor drawings as
approved for construction of any emission-control devices and specifications of
any other major equipment in the emission-control system in sufficient detail
to demonstrate that the requirements of the Design Criteria will be
satisfied;
(d) No later than nine
months after receiving the DEQ's approval of the Design Criteria, the owner or
operator must begin construction of any emission-control devices;
(e) No later than fourteen months after
receiving the DEQ's approval of Design Criteria, the owner or operator must
complete construction in accordance with the Design Criteria;
(f) No later than October 15, 2014, the owner
or operator must demonstrate compliance with the applicable requirements
identified in OAR 340-240-0500 through 0540.
Compliance with 340-240-0510 must be
demonstrated by conducting a source test. Compliance with
340-240-0520 and 0530 must be
demonstrated by implementing the approved plans.
(2) Section (1) of this rule does not apply
if the owner or operator of the source has demonstrated by September 15, 2014
that the source is capable of being operated and is operated in continuous
compliance with applicable requirements of OAR
340-240-0500 through
340-240-0540 and the DEQ has
agreed with the demonstration in writing. The DEQ may grant an extension until
April 15, 2015 for a source to demonstrate compliance under this section. The
applicable requirements will be incorporated in the Permit issued to the
source.
(3) The DEQ may adjust the
schedule specified in subsections (1)(a) through (e) of this rule if necessary
to ensure timely compliance with subsection (1)(f) of this rule or if necessary
to conform to an existing compliance schedule with an earlier compliance
demonstration date.
NOTE: These rules are included in the State of Oregon Clean Air Act Implementation Plan as adopted by the Environmental Quality Commission under OAR 340-200-0040.
Notes
Stat. Auth.: ORS 468 & 468A
Stats. Implemented: ORS 468A.025
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.