Or. Admin. Code § 603-029-2610 - Thermal Processing
(1) Process
schedules. Prior to the processing of canned product for distribution in
commerce, a state-inspected establishment must have a process schedule (as
defined in OAR 603-029-2600) for each canned meat or poultry product to be
packed by the state-inspected establishment.
(2) Source of process schedules:
(a) Process schedules used by a
state-inspected establishment must be developed or determined by a processing
authority.
(b) Any change in
product formulation, ingredients, or treatments that are not already
incorporated in a process schedule and that may adversely affect either the
product heat penetration profile or sterilization value requirements must be
evaluated by the state-inspected establishment's processing authority. If it is
determined that any such change adversely affects the adequacy of the process
schedule, the processing authority must amend the process schedule
accordingly.
(c) Complete records
concerning all aspects of the development or determination of a process
schedule, including any associated incubation tests, must be made available by
the state-inspected establishment to the Department upon request.
(3) Submittal of process
information.
(a) Prior to the processing of
canned product for distribution in commerce, the state-inspected establishment
must provide the inspector at the state-inspected establishment with a list of
the process schedules (including alternate schedules) along with any additional
applicable information, such as the retort come-up, operating procedures, and
critical factors.
(b) Letters or
other written communications from a processing authority recommending all
process schedules must be maintained on file by the state-inspected
establishment. Upon request by the Department, the state-inspected
establishment must make available such letters or written communications (or
copies thereof). If critical factors are identified in the process schedule,
the state-inspected establishment must provide the inspector with a copy of the
procedures for measuring, controlling, and recording these factors, along with
the frequency of such measurements, to ensure that the critical factors remain
within the limits used to establish the process schedule. Once submitted, the
process schedules and associated critical factors and the procedures for
measuring (including the frequency), controlling, and recording of critical
factors must not be changed without the prior written submittal of the revised
procedures (including supporting documentation) to the inspector at the
state-inspected establishment.
Notes
Statutory/Other Authority: ORS 603.085, ORS 619.042 & ORS 619.046
Statutes/Other Implemented: ORS 619.042, ORS 619.046, ORS 603.055, ORS 619.026 & ORS 619.036