Or. Admin. Code § 660-012-0180 - Financially-Constrained Project List
(1)
Cities and counties shall include a financially-constrained project list in a
transportation system plan. Cities and counties shall use the prioritized
unconstrained project list developed as provided in OAR
660-012-0170 and the amount of
funding available developed as provided in OAR
660-012-0115 to produce the
financially-constrained project list.
(2) Cities, counties, Metro, and the state
may only develop, fund, and construct projects on the financially-constrained
project list.
(a) Cities and counties may only
submit projects on the financially-constrained project list in their
transportation system plan to the financially-constrained list of a
federally-required regional transportation plan.
(b) Cities and counties may develop, fund, or
construct a project on the unconstrained project list if:
(A) The project is required as a condition of
land development;
(B) A property
owner is providing financial or material contributions to the project;
and
(C) The project would not
require review as provided in OAR
660-012-0830.
(3) Cities and counties
shall create a financially-constrained project list using the top available
projects on the prioritized unconstrained project list and the planning-level
cost estimates developed as provided in OAR
660-012-0170. The sum of the
planning-level cost estimates for projects placed on the
financially-constrained project list shall not exceed 125 percent of the
funding available as identified in OAR
660-012-0115. Cities and
counties shall select projects such that the resulting financially-constrained
list would:
(a) Reduce per capita vehicle
miles traveled, as provided in OAR
660-012-0160;
(b) Burden underserved populations less than
and benefit underserved populations as much or more as the city or county
population as a whole; and
(c) Make
significant progress towards meeting the performance targets set for each
performance measure as provided in OAR
660-012-0910 or OAR
660-044-0110.
(4) If the list of projects cannot
meet each test in section (3), the city or county must adjust the project list
to find the highest-ranking set of projects that can meet the criteria in
section (3). This is the financially-constrained project list.
(5) Cities or counties making a major or
minor amendment to the transportation system plan as provided in OAR
660-012-0105 which includes an
update to any project list, shall update the financially-constrained project
list as provided in this rule.
(6)
Cities and counties shall prioritize the implementation of projects from the
financially-constrained project list for their ability to reduce climate
pollution and improve equitable outcomes using the criteria provided in section
(3) of this rule.
Notes
Statutory/Other Authority: ORS 197.040
Statutes/Other Implemented: ORS 184.899, ORS 197.012, ORS 197.712 & ORS 468A.205
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.