Or. Admin. Code § 660-046-0370 - Duration of Time Extension
(1)
As provided in OAR 660-046-0350(3)(f)(A),
the IBTER must specify when the local government intends to correct the
significant infrastructure deficiency. The IBTER must provide a detailed
timeline for a complete plan of action that will remedy the significant
infrastructure deficiency, which may include phased infrastructure improvements
and contingent actions and timelines based on circumstances outside the control
of the local government.
(2) If,
for reasons beyond the control of the local government, the local government
cannot complete an approved remediation plan by the deadline specified in the
time extension decision, the local government, prior to the expiration date of
a time extension, may prepare an amended remediation plan and submit the plan
for department consideration. With the exception of application deadlines
specified in OAR 660-046-0350(1),
the amended remediation plan must be consistent with the provisions of OAR
660-046-0300 through OAR
660-046-0370. The amended
remediation plan must explain why the initial approved plan could not be
completed on schedule. Department review of the amended remediation plan is not
subject to the completeness review period specified in OAR
660-046-0350(2),
nor the required decision timelines in OAR
660-046-0360(4).
Otherwise, the review process and criteria for the amended remediation plan
must be consistent with the requirements of OAR
660-046-0360. Additionally, the
department shall evaluate the following considerations in review of any amended
remediation plan:
(a) Whether the local
government anticipated or reasonably should have anticipated the contingencies
causing delay in the initial remediation plan;
(b) Whether additional delay in the enactment
of middle housing allowances is warranted; and
(c) Whether the allowance for middle housing
in the subject area would provide an opportunity for other parties to construct
the necessary infrastructure as needed in association with middle housing
development.
(3) Upon
the expiration date of a time extension, the local government must either enact
development code regulations implementing middle housing or apply the model
code, as applicable, per OAR
660-046-0100 or OAR
660-046-0200.
Notes
Statutory/Other Authority: ORS 197.040 & OR Laws 2019, chapter 639, section 4(6)
Statutes/Other Implemented: ORS 197.758 & OR Laws 2019, chapter 639, sections 3 and 4
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.