Or. Admin. Code § 731-005-0570 - Solicitation Protest; Request for Change; Request for Clarification
(1) Protest.
(a) Delivery. An Offeror may protest
Specifications or Contract terms and conditions. Unless otherwise specified in
the Solicitation Document, an Offeror must deliver a Written protest to ODOT
not less than 10 Days prior to Closing.
(b) Content of Protest.
(A) An Offeror's Written protest shall
include:
(i) A detailed statement of the legal
and factual grounds for the protest;
(ii) A description of the resulting prejudice
to the Offeror; and
(iii) A
statement of the desired changes to the Contract terms and conditions,
including Specifications.
(B) An Offeror shall mark its protest as
follows:
(i) Solicitation Specification or
Contract Provision Protest; and
(ii) Solicitation Document Number (or Other
Identification as specified in the Solicitation
Document).
(2) Request for Change.
(a) Delivery. An Offeror may request in
Writing a change to the Specifications or Contract terms and conditions. Unless
otherwise specified in the Solicitation Document, an Offeror must deliver the
Written request for change to ODOT not less than 10 Days prior to
Closing;
(b) Content of Request or
Change.
(A) An Offeror's Written request for
change shall include a statement of the requested changes to the Contract terms
and conditions, including Specifications together with the reason for the
requested change.
(B) An Offeror
shall mark its request for change as follows:
(i) Solicitation Specification or Contract
Provision Request for Change; and
(ii) Solicitation Document Number (or Other
Identification as specified in the Solicitation Document).
(3) Agency response.
ODOT is not required to consider an Offeror's request for change or protest
after the deadline established for submitting such request or protest. ODOT
shall provide notice to the applicable Entity if it entirely rejects a protest.
If ODOT agrees with the Entity's request or protest, in whole or in part, ODOT
shall either issue an Addendum reflecting its determination under OAR
731-005-0580 or cancel the
Solicitation under OAR
731-005-0720.
(4) Extension of Closing. If ODOT receives a
Written request for change or protest from an Offeror in accordance with this
rule, ODOT may extend Closing if ODOT determines an extension is necessary to
consider the request or protest and to issue an Addendum, if any, to the
Solicitation Document.
(5)
Clarification. Prior to the deadline for submitting a Written request for
change or protest, an Offeror may request that ODOT clarify any provision of
the Solicitation Document. ODOT's clarification to an Offeror, whether orally
or in Writing, does not change the Solicitation Document and is not binding on
ODOT unless ODOT amends the Solicitation Document by
Addendum.
Notes
Stat. Auth.: ORS 184.616, 184.619, 279A.050 & 279A.065
Stats. Implemented: ORS 279C.305, 279C.345, 279C.365 & 279C.460