Tenn. Comp. R. & Regs. 0780-02-23-.08 - FEES
(1) The fee shall be payable in full at the
time of application for a building permit. The fee shall be determined based on
actual expected construction costs; however, the actual costs shall not be less
than the construction cost based on the latest available Building Valuation
Data published by the International Code Council (using a 0.60 Cost Modifier,
except for the footnotes). The fee for a permit for construction shall be as
specified in the following table:
|
Total Construction Cost |
Fee |
|
$0.00 to $5,000 |
$100 |
|
$5,001 to $100,000 |
$350 |
|
$100,001 to $150,000 |
$400 |
|
$150,001 to $200,000 |
$450 |
|
$200,001 to $250,000 |
$500 |
|
$250,001 to $300,000 |
$550 |
|
$300,001 AND UP |
$550 for the first $300,000; plus $50.00 for each additional fifty thousand dollars ($50,000) above $300,000 or fraction thereof. |
(a) When the
permit fee is to be collected from another state department or agency, the
permit may be issued once all information needed to invoice or journal voucher
the other state department or agency has been received.
(b) If the application for a building permit
must be resubmitted because its issuance has become invalid under paragraph (3)
of rule 0780-02-23-.05, the fee
established in this rule shall be imposed.
(2) After October 1, 2011, the fee for a
plumbing and mechanical inspection shall be one hundred dollars ($100.00) in
addition to other applicable fees.
(3) The fee for a slab inspection, other than
monolith pours, shall be one hundred dollars ($100.00) in addition to other
applicable fees.
(4) The fee for a
prefabricated wall inspection shall be one hundred dollars ($100.00) in
addition to other applicable fees.
(5) The fee for a re-inspection necessitated
by more than one (1) rejection on a project shall be one hundred dollars
($100.00).
(6) The fee for a
consultation inspection or a temporary certificate of occupancy shall be one
hundred dollars ($100.00).
(7) The
Division may require appropriate documentation of costs (such as contractors'
bids or invoice) if:
(a) In the Division's
opinion, the construction cost of a project has been underestimated in a permit
application based on the latest available Building Valuation Data published by
the International Code Council (using a 0.60 Cost Modifier, except for the
footnotes).
(b) After initial
review, if such documentation warrants an additional permit charge it shall be
computed, assessed, and paid promptly and no further construction shall be
authorized pursuant to the authority of the permit until payment is
made.
(8) If a permit
expires before completion of a project or a project is stopped before its
completion, the permit holder shall be entitled to a refund of the inspection
fees that would have been due to the deputy building inspector under their
contract for any required inspection under Tenn. Comp. R. & Regs.
0780-02-23-.08 that was not performed, provided that the permit holder requests
such refund on a form prescribed by the Division no less than sixty (60) days
prior to the expiration of the permit.
(9) Any person who begins any work on any
building or structure before obtaining the necessary permit required under this
chapter shall be subject to an additional fee of one hundred percent (100%) of
the required permit fee for each violation.
Notes
Authority: T.C.A. ยง 68-120-101(a), (b) and (d).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.