Utah Admin. Code R131-1-12 - Direct Awards
(1) The Executive
Director may award a contract to an architectural/engineering firm without
following the procedures of this rule if:
(a)
The contract is for a project which is integrally related to, or an extension
of, a project which was awarded to the architectural/engineering
firm;
(b) The
architectural/engineering firm performed satisfactorily on any similar or
related project; and
(c) The
Executive Director determines that the direct award is in the best interests of
the State.
(2) The
Executive Director shall place written documentation of the reasons for the
direct award in the project file and shall report the action to the Board at
its next meeting.