Utah Admin. Code R23-1-1306 - Special Provisions Regarding Construction Manager/General Contractor
(1) In the
selection of a construction manager/general contractor, a standard procurement
process as defined in Section
63G-6a-103 may be used or an
exception allowed under Part 8 of the Utah Procurement Code.
(2) When the construction manager/general
contractor enters into any subcontract that was not specifically included in
the construction manager/general contractor's cost proposal, the construction
manager/general contractor shall procure the subcontractors by using a standard
procurement process as defined in Section 63G-6a-103 or an exception to the
requirement to use a standard procurement process, described in Part 8 of the
Utah Procurement Code.