Utah Admin. Code R23-3-5 - Funding of Programs
Programming may be funded from one of the following sources.
(1) Funds appropriated for
that purpose by the Legislature.
(2) Funds provided by the agency.
(a) This would typically be the funding
source for the development of a program document before the Legislature funds
the project.
(b) Funds advanced by
agencies for programming costs may be included in the project budget request,
but no assurance can be given that project funds will be available to reimburse
the agency.
(c) Agencies that
advance funds for programming that would otherwise lapse may not be reimbursed
in a subsequent fiscal year.
(3) If an agency can demonstrate to the
director that there is no other funding source for programming for a project
that is likely to be funded in the upcoming legislative session, it may request
to borrow funds from the planning fund as provided for in Section
R23-3-8.