Utah Admin. Code R23-5-7 - Use of Statewide Contingency Reserve
(1) The statewide contingency reserve may
provide additional funding to a project when:
(a) necessary construction costs arise on
projects after the construction has been bid;
(b) costs for other elements of a project
exceed the amount budgeted; or
(c)
necessary costs arise which were not budgeted for.
(2) Unbudgeted costs included in Subsection
R23-5-6(1)(c)
may include legal services, insurance, surveys, testing and inspection, and
bidding costs.
(3) The statewide
contingency reserve may be used to fund changes in scope only if the scope
change is necessary for the proper functioning of the program that was provided
for in the approved project scope. The division shall take steps as necessary
to minimize the utilization of the statewide contingency reserve for scope
changes.
(4) With the prior
approval of the director, the statewide contingency reserve may be used to fund
unanticipated costs on projects funded through non-appropriated
funds.