Utah Admin. Code R277-471-6 - School Construction Inspections
(1) Before any school construction project
begins, the SDBO or CSBBO shall obtain a construction project number from the
Superintendent by completing and submitting construction project identification
forms provided by the Superintendent and other required submittals for all
projects consistent with Title 53E, Chapter 3, Part 7, School Construction, and
the manual.
(2) A certified plans
examiner shall approve all LEA school plans and specifications before any LEA
construction project begins.
(3)
(a) If an LEA cannot provide appropriate and
proper school construction inspection and plan review services, the
Superintendent may procure inspection services and charge the LEA for those
services.
(b) An approved inspector
shall establish fees in advance of inspection services.
(4) LEA construction projects shall comply
with Title 53E, Chapter 3, Part 7, School Construction, and this Rule R277-471
to:
(a) ensure that each inspector is
adequately and appropriately credentialed;
(b) identify and provide to the
Superintendent and local government entity building official reports of all
inspections with the name, state license number, and disciplines of each
inspector performing the project inspections;
(c) submit inspection certificates and all
related submittals to the Superintendent and appropriate local government
entity building official;
(d)
submit inspection summary reports monthly to the appropriate local government
entity building official and the Superintendent;
(e) sign the final certificate of inspection
and verification form, certifying all inspections were completed in compliance
with all applicable laws and rules to safeguard the public health, safety, and
general welfare of occupants;
(f)
send the final inspection certification, inspection verification, and provide
all other related project closeout submittals to the Superintendent and to the
appropriate local government entity building official upon completion of the
project; and
(g) maintain all
submitted documentation at a designated LEA location for auditing or
monitoring.
(5) The SDBO
or CSBBO may submit either paper or electronic reports to satisfy this
section.