Utah Admin. Code R307-401-6 - Review Period
(1) Completeness
Determination. Within 30 days after receipt of a notice of intent, or any
additional information necessary to the review, the director will advise the
applicant of any deficiency in the notice of intent or the information
submitted.
(2) Within 90 days after
the receipt of a complete application including the information described in
Section R307-401-5, the director will
(a) issue an approval order for the proposed
construction, installation, modification, relocation, or establishment pursuant
to the requirements of Section
R307-401-8; or
(b) issue an order prohibiting the proposed
construction, installation, modification, relocation or establishment if it is
determined that any part of the proposal will not be in the accord with the
requirements of Title R307.
(3) The review period under Subsection
R307-401-6(2)
may be extended by up to three 30-day extensions if more time is needed to
review the proposal.