Utah Admin. Code R315-265-1060 - Air Emission Standards for Equipment Leaks - Standards: Closed-Vent Systems and Control Devices

(a) Owners and operators of closed-vent systems and control devices subject to Sections R315-265-1050 through R315-265-1064 shall comply with Section R315-265-1033.
(b)
(1) The owner or operator of an existing facility who cannot install a closed-vent system and control device to comply with Sections R315-265-1050 through R315-265-1064 on the effective date that the facility becomes subject to Sections R315-265-1050 through R315-265-1064 shall prepare an implementation schedule that includes dates that the closed-vent system and control device will be installed and in operation. The controls shall be installed as soon as possible, but the implementation schedule may allow up to 30 months after the effective date that the facility becomes subject to Sections R315-265-1050 through R315-265-1064 for installation and startup.
(2) Any units that begin operation after December 21, 1990, and are subject to Sections R315-265-1050 through R315-265-1064 when operation begins, shall comply with the rules immediately, in other words, shall have control devices installed and operating on startup of the affected unit, the 30-month implementation schedule does not apply.
(3) The owner or operator of any facility in existence on the effective date of a statutory, EPA regulatory, or Utah Administrative Code amendment that makes the facility subject to Sections R315-265-1050 through R315-265-1064 shall comply with the requirements of Sections R315-265-1050 through R315-265-1064 as soon as practicable but no later than 30 months after the amendment's effective date. If control equipment required by Sections R315-265-1050 through R315-265-1064 cannot be installed and begin operation by the effective date of the amendment, the facility owner or operator shall prepare an implementation schedule that includes the following information:
(i) specific calendar dates for award of contracts or issuance of purchase orders for the control equipment;
(ii) initiation of on-site installation of the control equipment;
(iii) completion of the control equipment installation; and
(iv) performance of any testing to demonstrate that the installed equipment meets the applicable standards of Sections R315-265-1050 through R315-265-1064.
(v) The owner or operator shall enter the implementation schedule in the operating record or in a permanent, readily available file located at the facility.
(4) Owners and operators of facilities and units that become newly subject to the requirements of Sections R315-265-1050 through R315-265-1064 after December 8, 1997 due to an action other than those described in Subsection R315-265-1060(b)(3) shall comply with the applicable requirements immediately, in other words, shall have control devices installed and operating on the date the facility or unit becomes subject to Sections R315-265-1050 through R315-265-1064, the 30-month implementation schedule does not apply.

Notes

Utah Admin. Code R315-265-1060
Adopted by Utah State Bulletin Number 2025-02, effective 1/13/2025

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.