Utah Admin. Code R315-265-112 - Closure and Post-Closure - Closure Plan; Amendment of Plan
(a) Written plan. By May 19, 1981, or by six
months after the effective date of the rule that first subjects a facility to
provisions of Section R315-265-112, the owner or operator of a hazardous waste
management facility shall have a written closure plan . Until final closure is
completed and certified in accordance with Section R315-265-115, a copy of the
most current plan shall be furnished to the Director upon request, including
request by mail. In addition, for facilities without approved plans, it shall
also be provided during site inspections, on the day of inspection , to any
officer, employee, or representative of the Director who is duly designated by
the Director .
(b) Content of plan.
The plan shall identify steps necessary to perform partial, final, or both,
closure of the facility at any point during its active life. The closure plan
shall include, at least:
(1) A description of
how each hazardous waste management unit at the facility will be closed in
accordance with Section R315-265-111; and
(2) A description of how final closure of the
facility will be conducted in accordance with Section R315-265-111. The
description shall identify the maximum extent of the operation which will be
unclosed during the active life of the facility ; and
(3) An estimate of the maximum inventory of
hazardous wastes ever on-site over the active life of the facility and a
detailed description of the methods to be used during partial and final
closure, including, but not limited to methods for removing, transporting,
treating, storing or disposing of all hazardous waste , identification of and
the type(s) of off-site hazardous waste management unit(s) to be used, if
applicable; and
(4) A detailed
description of the steps needed to remove or decontaminate all hazardous waste
residues and contaminated containment system components, equipment, structures,
and soils during partial and final closure including, but not limited to,
procedures for cleaning equipment and removing contaminated soils, methods for
sampling and testing surrounding soils, and criteria for determining the extent
of decontamination necessary to satisfy the closure performance standard;
and
(5) A detailed description of
other activities necessary during the partial and final closure periods to
ensure that all partial closures and final closure satisfy the closure
performance standards, including, but not limited to, ground-water monitoring ,
leachate collection, and run-on and run-off control; and
(6) A schedule for closure of each hazardous
waste management unit and for final closure of the facility . The schedule shall
include, at a minimum, the total time required to close each hazardous waste
management unit and the time required for intervening closure activities which
will allow tracking of the progress of partial and final closure. For example,
in the case of a landfill unit, estimates of the time required to treat or
dispose of all hazardous waste inventory and of the time required to place a
final cover shall be included.; and
(7) An estimate of the expected year of final
closure for facilities that use trust funds to demonstrate financial assurance
under Sections R315-265-143 or 265-145 and whose remaining operating life is
less than twenty years, and for facilities without approved closure
plans.
(8) For facilities where the
Director has applied alternative requirements at a regulated unit under
Subsections R315-265-90(f), R315-265-110(d), R315-265-140(d), or all three,
either the alternative requirements applying to the regulated unit, or a
reference to the enforceable document containing those alternative
requirements.
(c)
Amendment of plan. The owner or operator may amend the closure plan at any time
prior to the notification of partial or final closure of the facility . An owner
or operator with an approved closure plan shall submit a written request to the
Director to authorize a change to the approved closure plan . The written
request shall include a copy of the amended closure plan for approval by the
Director .
(1) The owner or operator shall
amend the closure plan whenever:
(i) Changes
in operating plans or facility design affect the closure plan , or
(ii) There is a change in the expected year
of closure, if applicable, or
(iii)
In conducting partial or final closure activities, unexpected events require a
modification of the closure plan .
(iv) The owner or operator requests the
Director to apply alternative requirements to a regulated unit under
Subsections R315-265-90(f), R315-265-110(d), R315-265-140(d), or all
three.
(2) The owner or
operator shall amend the closure plan at least 60 days prior to the proposed
change in facility design or operation, or no later than 60 days after an
unexpected event has occurred which has affected the closure plan . If an
unexpected event occurs during the partial or final closure period, the owner
or operator shall amend the closure plan no later than 30 days after the
unexpected event. These provisions also apply to owners or operators of surface
impoundments and waste piles who intended to remove all hazardous wastes at
closure, but are required to close as landfills in accordance with
40 CFR
265.310, which is adopted and incorporated by
reference.
(3) An owner or operator
with an approved closure plan shall submit the modified plan to the Director at
least 60 days prior to the proposed change in facility design or operation, or
no more than 60 days after an unexpected event has occurred which has affected
the closure plan . If an unexpected event has occurred during the partial or
final closure period, the owner or operator shall submit the modified plan no
more than 30 days after the unexpected event. These provisions also apply to
owners or operators of surface impoundments and waste piles who intended to
remove all hazardous wastes at closure but are required to close as landfills
in accordance with
40 CFR
265.310, which is adopted and incorporated by
reference. If the amendment to the plan is a Class 2 or 3 modification
according to the criteria in Section
R315-270-42,
the modification to the plan will be approved according to the procedures in
Subsection R315-265-112(d) (4).
(4)
The Director may request modifications to the plan under the conditions
described in Subsection R315-265-112(c)(1). An owner or operator with an
approved closure plan shall submit the modified plan within 60 days of the
request from the Director , or within 30 days if the unexpected event occurs
during partial or final closure. If the amendment is considered a Class 2 or 3
modification according to the criteria in Section
R315-270-42,
the modification to the plan will be approved in accordance with the procedures
in Subsection R315-265-112(d)(4).
(d) Notification of partial closure and final
closure.
(1) The owner or operator shall
submit the closure plan to the Director at least 180 days prior to the date on
which he expects to begin closure of the first surface impoundment, waste pile,
land treatment, or landfill unit, or final closure if it involves such a unit,
whichever is earlier. The owner or operator shall submit the closure plan to
the Director at least 45 days prior to the date on which he expects to begin
partial or final closure of a boiler or industrial furnace. The owner or
operator shall submit the closure plan to the Director at least 45 days prior
to the date on which he expects to begin final closure of a facility with only
tanks, container storage, or incinerator units. Owners or operators with
approved closure plans shall notify the Director in writing at least 60 days
prior to the date on which he expects to begin closure of a surface
impoundment, waste pile, landfill, or land treatment unit, or final closure of
a facility involving such a unit. Owners or operators with approved closure
plans shall notify the Director in writing at least 45 days prior to the date
on which he expects to begin partial or final closure of a boiler or industrial
furnace. Owners or operators with approved closure plans shall notify the
Director in writing at least 45 days prior to the date on which he expects to
begin final closure of a facility with only tanks, container storage, or
incinerator units.
(2) The date
when he "expects to begin closure" shall be either:
(i) Within 30 days after the date on which
any hazardous waste management unit receives the known final volume of
hazardous wastes, or, if there is a reasonable possibility that the hazardous
waste management unit will receive additional hazardous wastes, no later than
one year after the date on which the unit received the most recent volume of
hazardous waste . If the owner or operator of a hazardous waste management unit
can demonstrate to the Director that the hazardous waste management unit or
facility has the capacity to receive additional hazardous wastes and he has
taken, and will continue to take, all steps to prevent threats to human health
and the environment, including compliance with all interim status requirements,
the Director may approve an extension to this one-year limit; or
(ii) For units meeting the requirements of
Subsection R315-265-113(d), no later than 30 days after the date on which the
hazardous waste management unit receives the known final volume of nonhazardous
wastes, or if there is a reasonable possibility that the hazardous waste
management unit will receive additional nonhazardous wastes, no later than one
year after the date on which the unit received the most recent volume of
nonhazardous wastes. If the owner or operator can demonstrate to the Director
that the hazardous waste management unit has the capacity to receive additional
nonhazardous wastes and he has taken, and will continue to take, all steps to
prevent threats to human health and the environment, including compliance with
all applicable interim status requirements, the Director may approve an
extension to this one-year limit.
(3) The owner or operator shall submit his
closure plan to the Director no later than 15 days after:
(i) Termination of interim status except when
a permit is issued simultaneously with termination of interim status;
or
(ii) Issuance of a judicial
decree or final order under section 3008 of RCRA to cease receiving hazardous
wastes or close.
(4) The
Director will provide the owner or operator and the public, through a newspaper
notice, the opportunity to submit written comments on the plan and request
modifications to the plan no later than 30 days from the date of the notice. He
will also, in response to a request or at his own discretion, hold a public
hearing whenever such a hearing might clarify one or more issues concerning a
closure plan . The Director will give public notice of the hearing at least 30
days before it occurs. Public notice of the hearing may be given at the same
time as notice of the opportunity for the public to submit written comments,
and the two notices may be combined. The Director will approve, modify, or
disapprove the plan within 90 days of its receipt. If the Director does not
approve the plan he shall provide the owner or operator with a detailed written
statement of reasons for the refusal and the owner or operator shall modify the
plan or submit a new plan for approval within 30 days after receiving such
written statement. The Director will approve or modify this plan in writing
within 60 days. If the Director modifies the plan, this modified plan becomes
the approved closure plan . The Director shallt assure that the approved plan is
consistent with Sections R315-265-111 through 265-115 and the applicable
requirements of Sections R315-265-90 through 265-94, and Sections R315-265-197,
R315-265-228, R315-265-258, and
40 CFR
265.280,
265.310,
265.351,
265.381,
265.404, and
265.1102,
which are adopted and incorporated by reference. A copy of the modified plan
with a detailed statement of reasons for the modifications shall be mailed to
the owner or operator.
(e) Removal of wastes and decontamination or
dismantling of equipment. Nothing in Section R315-265-112 shall preclude the
owner or operator from removing hazardous wastes and decontaminating or
dismantling equipment in accordance with the approved partial or final closure
plan at any time before or after notification of partial or final
closure.