Utah Admin. Code R746-312-10 - Level 3 Interconnection Review
(1) A generating facility that meets the
following criteria is eligible for Level 3 interconnection review:
(a) the generating facility has a capacity of
greater than two megawatts but no larger than 20 megawatts;
(b) the generating facility is not certified;
or
(c) the generating facility does
not qualify for or failed to meet Level 1 or Level 2 interconnection review
requirements.
(2) A
public utility must process, evaluate, and approve, if appropriate, each Level
3 request for interconnection according to the following steps unless the
public utility has received approval from the commission for an alternative
Level 3 interconnection review method:
(a)
The public utility shall date and time stamp each interconnection request on
the day it was received by the public utility.
(b) Within three business days after receipt
of an interconnection request, the public utility shall acknowledge to the
interconnection customer receipt of the interconnection request.
(c) Within ten business days after receipt of
an interconnection request, the public utility shall evaluate the
interconnection request and notify the interconnection customer whether the
interconnection request is complete.
(i) If
the interconnection request is not complete, the public utility must provide a
list detailing the information that must be provided to finish the
application.
(ii) Within ten
business days of receipt of this notification, the interconnection customer
must submit the missing information to the public utility or request an
extension of time to provide the information. If the interconnection customer
does not provide the listed information or request an extension of time within
the ten-business day deadline, the interconnection request shall be considered
withdrawn.
(iii) An interconnection
request shall be considered complete upon submission of the listed
information.
(d) Scoping
Meeting. If requested, a scoping meeting shall be held as follows within ten
business days after the interconnection request is considered complete, or as
otherwise mutually agreed to by the parties:
(i) The public utility and the
interconnection customer shall bring to the meeting personnel, including system
engineers and other resources, as may be reasonably required to accomplish the
purpose of the meeting;
(ii) The
purpose of the scoping meeting is to:
(A)
discuss the interconnection request and review existing studies relevant to the
interconnection request; and
(B)
discuss whether the public utility should perform a feasibility study or
proceed directly to a system impact study, a facilities study, or an
interconnection agreement;
(iii) Scoping meeting follow-up:
(A) If the parties agree that a feasibility
study should be performed, the public utility shall provide the interconnection
customer as soon as possible, but no later than five business days after the
scoping meeting, a feasibility study agreement including an outline of the
scope of the study and a non-binding, good faith estimate of the cost to
perform the study.
(B) If the
parties agree not to perform a feasibility study but rather proceed directly to
the system impact study, the public utility shall, no later than five business
days after the scoping meeting, provide the interconnection customer with a
system impact study agreement including an outline of the scope of the study
and a non-binding, good faith estimate of the cost to perform the
study.
(iv) The scoping
meeting may be omitted by mutual agreement. If the scoping meeting is omitted,
the public utility, if requested by the interconnection customer, must provide
information pertinent to the interconnection request, for example, the
available fault current at the proposed interconnection location, the peak
loading on the lines in the general vicinity of the generating facility, and
the configuration of the distribution lines at the proposed point of common
coupling, within ten business days after the interconnection request is
considered complete.
(e)
Feasibility Study. A feasibility study shall provide a preliminary evaluation
of the system impact that would result from interconnecting the generating
facility and the cost of interconnecting the generating facility to the public
utility's electric distribution system and shall be finished as follows:
(i) For interconnection customers opting to
forgo a scoping meeting and proceeding directly to the feasibility study, the
public utility shall provide the interconnection customer, as soon as possible
but no later than ten business days after receipt of a completed application, a
standard form feasibility study agreement including an outline of the scope of
the study and a non-binding, good faith estimate of the cost to perform the
study.
(ii) To remain in
consideration for interconnection, an interconnection customer who has
requested or requires a feasibility study, either as part of or independent of
a scoping meeting, must return the executed feasibility study agreement within
30 business days of receipt. A deposit of the lesser of 50% of the good faith
estimate or earnest money of $1,000 may be required from the interconnection
customer.
(iii) Within 30 business
days of receipt of an executed study agreement and payment of any required
deposit, the public utility shall conduct the feasibility study and notify the
interconnection customer either:
(A) the
feasibility study shows no potential for adverse system impacts, no facilities
are required, and the interconnection request is approved, in which case the
public utility shall send the interconnection customer an executable
interconnection agreement within five business days;
(B) the feasibility study shows no potential
for adverse system impacts; however, additional facilities may be required and
the review process shall proceed to a facilities study. When proceeding to a
facilities study, the public utility shall provide the interconnection customer
a standard form facilities study agreement, including an outline of the scope
of the study and a non-binding, good faith estimate of the cost to perform the
study within five business days; or
(C) the feasibility study shows the potential
for adverse system impacts, and the review process shall proceed to a system
impact study. When proceeding to a system impact study, the public utility
shall provide the interconnection customer with a standard form system impact
study agreement including an outline of the scope of the study and a
non-binding, good faith estimate of the cost to perform the study within 15
business days of transmittal of the feasibility study report.
(iv) Any feasibility study fees
will be invoiced to the interconnection customer after the feasibility study is
completed and delivered and will include a summary of professional time. The
interconnection customer must pay any study costs that exceed the deposit
without interest within 30 calendar days of receipt of the invoice or
resolution of any dispute but this payment responsibility shall be limited to
and not exceed 125% of the public utility's non-binding, good faith estimate
for the study. If the deposit exceeds the invoiced fees, the public utility
shall refund the excess within 30 calendar days of the invoice without
interest.
(f) System
Impact Study. Any required system impact study must be conducted in accordance
with good utility practice and shall be finished as follows:
(i) The system impact study shall:
(A) provide details on the impacts to the
electric distribution system that would result if the generating facility were
interconnected without modifications to either the generating facility or to
the electric distribution system;
(B) identify any modifications to the public
utility's electric distribution system necessary to accommodate the proposed
interconnection;
(C) focus on power
flows and utility protective devices, including control requirements;
and
(D) include the following
elements, as applicable:
(I) a load flow
study;
(II) a short-circuit
study;
(III) a circuit protection
and coordination study;
(IV) the
impact on the operation of the electric distribution system;
(V) a stability study, along with the
conditions that would justify including this element in the impact
study;
(VI) a voltage collapse
study, along with the conditions that would justify including this element in
the impact study; and
(VII)
additional elements, if justified by the public utility and approved in writing
by the public utility and the interconnection customer before the impact
study.
(ii) To
remain in consideration for interconnection, an interconnection customer who
has requested a system impact study, either as part of or independent of a
scoping meeting or feasibility study, must return the executed impact study
agreement within 30 business days of receipt of the agreement. A deposit of the
good faith estimated costs for each system impact study may be required from
the interconnection customer.
(iii)
After the applicant executes the system impact study agreement and pays any
required deposit, the public utility shall finish the impact study and
distribute the results to the interconnection customer within 30 business days,
or 45 business days for transmission impact studies, notifying the
interconnection customer either:
(A) Only
minor modifications to the public utility's electric distribution or
transmission system are necessary to accommodate interconnection. In this case,
the public utility must:
(I) provide to the
interconnection customer at the same time the detail of the scope of the
necessary modifications, a non-binding, good faith estimate of their cost, and
an executable interconnection agreement; and
(II) approve the interconnection request upon
receipt of the executed interconnection agreement from the interconnection
customer.
(B)
Modifications to the public utility's electric distribution system or
transmission system are necessary to accommodate the proposed interconnection
in which case the public utility must provide at the same time either:
(I) a non-binding, good faith estimate of the
cost of the modifications, if known; and
(II) a standard form facilities study
agreement including an outline of the scope of the study and a non-binding,
good faith estimate of the cost to perform the facilities study.
(iv) If the proposed
interconnection may affect electric transmission or delivery systems other than
those controlled by the public utility, operators of those other systems may
need additional studies to determine the potential impact of the
interconnection on those systems. If additional studies are required, the
public utility must coordinate the studies but will not be responsible for
their timing. The applicant shall be responsible for the costs of each
additional study required by another affected system. These studies will be
conducted only after the applicant has provided written
authorization.
(v) Any study fees
will be invoiced to the interconnection customer after the system impact study
is completed and delivered and will include a summary of professional time. The
interconnection customer must pay any study costs that exceed the deposit
without interest within 30 calendar days of receipt of the invoice or
resolution of any dispute but this payment responsibility shall be limited to
and not exceed 125% of the public utility's non-binding, good faith estimate
for the study. If the deposit exceeds the invoiced fees, the public utility
shall refund the excess within 30 calendar days of the invoice without
interest.
(g) Facilities
Study. The results of the facilities study shall specify a non-binding, good
faith cost estimate of the equipment, engineering, procurement, and
construction work, including overheads, needed to implement the conclusion of
the system impact study for the interconnection customer to safely interconnect
the generating facility with the public utility's electric distribution system
and the time required to build and install those facilities. The following
provisions apply to the facilities study:
(i)
A public utility may require a deposit of the good faith estimated costs for
the facilities study.
(ii) To
remain under consideration for interconnection, the interconnection customer
must return the executed facilities study agreement and any required deposit,
or request an extension of time, within 30 business days.
(iii) Design for any required interconnection
facilities or upgrades shall be performed under the facilities study agreement.
The public utility may contract with consultants to perform activities required
under the facilities study agreement. The interconnection customer and the
public utility may agree to allow the interconnection customer to separately
arrange for the design of some of the interconnection facilities. In these
cases, facilities design will be reviewed, modified, or both, before acceptance
by the public utility under the facilities study agreement. If the parties
agree to separately arrange for design and construction, and, provided security
and confidentiality requirements may be met, the public utility shall make
sufficient information available to the interconnection customer in accordance
with confidentiality and critical infrastructure requirements to permit the
interconnection customer to get an independent design and cost estimate for any
necessary facilities.
(iv) If
upgrades are required, the facilities study must be completed and the
facilities study report transmitted to the interconnection customer within 45
business days of the public utilities receipt of the facilities study agreement
from the interconnection customer. If no upgrades are necessary, and the
required facilities are limited to interconnection facilities, the facilities
study must be completed and the facilities study report transmitted to the
interconnection customer within 30 business days of the public utilities
receipt of the facilities study agreement from the interconnection customer.
The report, and any ensuing interconnection agreement, must list the conditions
and facilities necessary for the generating facility to safely interconnect
with the public utility's electric distribution system, and must include a
non-binding, good faith estimate of the cost of those facilities and the
estimated time required to build and install those facilities.
(v) Upon completion of the facilities study
and receipt of agreement of the interconnection customer to pay for
interconnection facilities and upgrades identified in the facilities study, the
public utility shall approve the interconnection request.
(vi) Any study fees will be invoiced to the
interconnection customer after the facilities study is completed and delivered
and will include a summary of professional time. The interconnection customer
must pay any study costs that exceed the deposit without interest within 30
calendar days of receipt of the invoice or resolution of any dispute, but this
payment responsibility shall be limited to and not exceed 125% of the public
utility's non-binding, good faith estimate for the study. If the deposit
exceeds the invoiced fees, the public utility shall refund the excess within 30
calendar days of the invoice without interest.
(h) Either before, along with, or within five
business days after notifying the interconnection customer that the
interconnection request has been approved, a public utility must provide the
procedures, requirements, and associated forms for final authorization of the
interconnection, as determined applicable by the public utility. These
procedures and requirements may include:
(i)
completion of any required inspection of the generating facility by the
building code official with jurisdiction over the generating facility and
transmittal to the public utility of appropriate documentation;
(ii) transmittal to the public utility of any
required notice of completion, notice of start-up, or interconnection
agreement;
(iii) installation of
any required meter modification by the public utility;
(iv) completion of any required inspection of
the generating facility before operation by the public utility; or
(v) the requirement that the applicant may
not begin parallel operations of the generating facility until receipt of a
final approval or authorization of interconnection.
(i) The customer and the public utility may
mutually agree to terms that vary from the standard form interconnection
agreement, but this non-standard agreement shall be subject to commission
approval.
(3) An
interconnection customer must notify the public utility of the anticipated
testing and inspection date of the generating facility at least ten business
days before testing, either through the submittal of the interconnection
agreement, a notice of completion, or in a separate notice.
(4) Within ten business days of receipt of
the required documentation, for example, the executed interconnection
agreement, notice of completion, or documentation of satisfactory completion of
inspections by non-company personnel, the public utility must, if it has not
already done so, conduct any company-required inspection or witness test, set
the new meter, if required, approve the interconnection, and provide written
notification to the interconnection customer of the final interconnection
authorization or approval and that the generating facility is authorized or
approved for parallel operation. If the public utility does not conduct the
witness test within ten business days or by mutual agreement of the parties,
the witness test is considered waived.
(5) Witness Test Not Acceptable: If the
witness test is conducted and is not acceptable to the public utility, the
interconnection customer must be granted a period of 60 business days to
resolve any deficiencies. The parties may mutually agree to extend the period
for resolving any deficiencies. If the interconnection customer fails to
address and resolve the deficiencies to the satisfaction of the public utility
within the agreed-upon period, the interconnection request is considered
withdrawn.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.