Utah Admin. Code R746-312-16 - Public Utility Maps, Records, and Reports
(1) Each public utility shall maintain
current records of interconnection customer generating facilities showing size,
location, generator type, and date of interconnection authorization.
(2) By July 1 of each year, each public
utility whose governing authority is the commission shall submit to the
commission an annual report with the following summary information for the
previous calendar year:
(a) the total number
of generating facilities approved and their associated attributes including
resource type, generating capacity, and zip code of the generating facility
location;
(b) the total rated
generating capacity of generating facilities by resource type;
(c) for net metering interconnections, the
total net excess generation kilowatt-hours received from interconnection
customers by month; and
(d) for net
metering interconnections, the total amount of excess generation credits in
kilowatt-hours, and their associated dollar value that have expired at the end
of each annualized billing period.