Utah Admin. Code R746-313-8 - Major Event Reporting by Electric Utilities
(1) Major event reporting for an electric
company whose governing authority is the commission. Within 30 business days
after the conclusion of each event which an electric company determines
satisfies the criteria for major event classification in accordance with IEEE
1366, the electric company shall file a major event report with the commission
for its consideration.
(2) The
major event report must include, at least:
(a)
a description of the major event, the interruption causes, and a summary of
restoration efforts and factors that affected restoration of service;
(b) identification of reliability reporting
area and geographic area affected;
(c) the total number of customers affected,
and the number of customers without service at periodic intervals;
(d) the calculated SAIDI, SAIFI, and CAIDI
impacts, that is, Event SAIDI, SAIFI, and CAIDI, associated with the major
event to customers for each reliability reporting area and system-wide;
and
(e) restoration of service
information including resources used and cost.