Utah Admin. Code R746-316-3 - Submission of an Electrical Power Delivery Quality Plan
(1) A qualified utility shall submit an
Electrical Power Delivery Quality Plan to the Commission on or before April 1,
2024 and biennially thereafter with subsequent Electrical Power Delivery
Quality Plans due on or before April 1 of each even-numbered year.
(2) A qualified utility's Electrical Power
Delivery Quality Plan must include:
(a) a
description of the metrics a qualified utility uses to assess Power Quality
against applicable Industry Standards;
(b) a description of the equipment the
qualified utility uses to assess Power Quality and to otherwise comply with
this rule;
(c) a description of the
procedures and standards the qualified utility will use to assess an
interconnection request to decrease the risk that the interconnected
utility-scale generation facility will adversely affect electrical power
delivery quality to customers;
(d)
a description of the procedures and standards the qualified utility will use to
address adverse effects to electrical power service quality that are caused by
interconnected customer-owned generation systems, including instances where the
adverse effects are discovered after the time of interconnection; and
(e) a description of proposed modifications
or upgrades to facilities and preventive programs the qualified utility will
implement to address any electrical power delivery quality issues that do not
meet the qualified utility's interconnection policy or relevant Industry
Standards.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.