Utah Admin. Code R746-440-1 - Filing Requirements for a Request for Approval of a Resource Decision
(1) A request for
approval of a Resource decision shall include testimony and exhibits which
provide:
(a) A description of the Resource
decision,
(b) Information to
demonstrate that the Energy utility has complied with the applicable
requirements of the Act and Commission rules,
(c) The purposes and reasons for the Resource
decision,
(d) An analysis of the
estimated or projected costs of the Resource decision, including the
engineering studies, data, information and models used in the Energy utility's
analysis,
(e) Descriptions and
comparisons of other resources or alternatives evaluated or considered by the
Energy utility, in lieu of the proposed Resource decision,
(f) Sufficient data, information,
spreadsheets, and models to permit an analysis and verification of the
conclusions reached and models used by the Energy utility,
(g) An analysis of the estimated effect of
the Resource decision on the Energy utility's revenue requirement,
(h) Financial information demonstrating
adequate financial capability to implement the Resource decision,
(i) Major contracts, if any, proposed for
execution or use in connection with the Resource decision,
(j) Information to show that the Energy
utility has or will obtain any required authorizations from the appropriate
governmental bodies for the Resource decision, and
(k) Other information as the Commission may
require.
(2) Notice of a
request for approval of a Resource decision.
(a) At least five calendar days prior to
filing a request for approval of a Resource decision, the Energy utility shall
provide public notice of its request for approval of a Resource decision. The
public notice shall provide a description of the request and information on how
interested persons my obtain, from the Energy utility, further information
about the request or a copy of the request.
(b) At least five calendar days prior to
filing a request for approval of a Resource decision, the Energy Utility shall
inform the Commission of the anticipated filing and the means by which the
Energy Utility has made, or will make, the public notice.
(3) Issues regarding the production,
treatment and use of materials of a confidential or proprietary nature,
including issues regarding who is entitled to review the materials, will be
determined by the Commission.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.