Utah Admin. Code R746-440-3 - Process for Review and Determination of a Request for an Order to Proceed with Implementation of an Approved Resource Decision
(1) A request for
such Commission review and determination shall include testimony and exhibits
which provide:
(a) An explanation of the
nature and cause of the change in circumstances or projected costs, including
how the Energy utility became aware of the change in circumstances or projected
cost and any action it has taken,
(b) An explanation of why an Order to Proceed
is or is not, in the Energy utility's view, the proper response to the changed
circumstances,
(c) The Energy
utility's updated projections regarding the impact of the changed circumstances
or projected costs on the timing, cost and other aspects of the approved
Resource decision,
(d) The costs
incurred to date in connection with the Resource decision,
(e) The Energy utility's updated projections
of any unavoidable costs if the approved Resource decision is not pursued to
completion, and
(f) Major proposed
contracts or contract amendments, if any, to be used in the event of an Order
to Proceed.
(2) Notice
of a request for review and determination of an Order to Proceed shall be
provided, by the Energy utility, to all parties in the docket in which the
Resource decision was approved and otherwise as determined by the
Commission.
(3) The Energy utility
shall maintain a complete record of its analyses and evaluations relating to
the Order to Proceed, including spreadsheets and models materially relied upon
by the utility, all materials submitted to the Commission and all materials
submitted in response to discovery requests during a proceeding involving a
review and determination for at least 10 years from the date of the
Commission's final order in a Commission proceeding for review and
determination of an Order to Proceed with Implementation of an approved
Resource decision. A party to a proceeding may petition the Commission to
require specified additional materials to be maintained for a specified
period.
(4) Issues regarding the
production, treatment and use of materials of a confidential or proprietary
nature, including issues regarding who is entitled to review those materials
will be determined by the Commission.