30 CFR 250.912 - What plans must I submit under the Platform Verification Program?

§ 250.912 What plans must I submit under the Platform Verification Program?
If your platform, associated structure, or major modification meets the criteria in § 250.910, you must submit the following plans to the Regional Supervisor for approval:
(a) Design verification plan. You may submit your design verification plan to BSEE with or subsequent to the submittal of your Development and Production Plan (DPP) or Development Operations Coordination Document (DOCD) to BOEM. Your design verification must be conducted by, or be under the direct supervision of, a registered professional civil or structural engineer or equivalent, or a naval architect or marine engineer or equivalent, with previous experience in directing the design of similar facilities, systems, structures, or equipment. For floating platforms, you must ensure that the requirements of the USCG for structural integrity and stability, e.g., verification of center of gravity, etc., have been met. Your design verification plan must include the following:
(1) All design documentation specified in § 250.905 of this subpart;
(2) Abstracts of the computer programs used in the design process; and
(3) A summary of the major design considerations and the approach to be used to verify the validity of these design considerations.
(b) Fabrication verification plan. The Regional Supervisor must approve your fabrication verification plan before you may initiate any related operations. Your fabrication verification plan must include the following:
(1) Fabrication drawings and material specifications for artificial island structures and major members of concrete-gravity and steel-gravity structures;
(2) For jacket and floating structures, all the primary load-bearing members included in the space-frame analysis; and
(3) A summary description of the following:
(i) Structural tolerances;
(ii) Welding procedures;
(iii) Material (concrete, gravel, or silt) placement methods;
(iv) Fabrication standards;
(v) Material quality-control procedures;
(vi) Methods and extent of nondestructive examinations for welds and materials; and
(vii) Quality assurance procedures.
(c) Installation verification plan. The Regional Supervisor must approve your installation verification plan before you may initiate any related operations. Your installation verification plan must include:
(1) A summary description of the planned marine operations;
(2) Contingencies considered;
(3) Alternative courses of action; and
(4) An identification of the areas to be inspected. You must specify the acceptance and rejection criteria to be used for any inspections conducted during installation, and for the post-installation verification inspection.
(d) You must combine fabrication verification and installation verification plans for manmade islands or platforms fabricated and installed in place.

Title 30 published on 2014-07-01.

No entries appear in the Federal Register after this date, for 30 CFR Part 250.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS

Title 30 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR Part 250 after this date.

  • 2015-04-20; vol. 80 # 75 - Monday, April 20, 2015
    1. 80 FR 21670 - Oil and Gas and Sulphur Operations on the Outer Continental Shelf—Requirements for Exploratory Drilling on the Arctic Outer Continental Shelf
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Ocean Energy Management, Bureau of Safety and Environmental Enforcement
      Extension of comment period for Notice of Proposed Rulemaking
      The comment period for the Notice of Proposed Rulemaking published on February 24, 2015, (80 FR 9916) has been extended. Written comments must be received by the extended due date of May 27, 2015. BOEM and BSEE may not fully consider comments received after this date. ADDRESSES: You may submit comments on the proposed rulemaking by any of the following methods. Please use the Regulation Identifier Number (RIN) 1082-AA00 as an identifier in your message. For comments specifically related to the draft Environmental Assessment conducted under the National Environmental Policy Act of 1969 (NEPA), please refer to NEPA in the heading of your message. • Federal eRulemaking Portal: http://www.regulations.gov. In the entry entitled “Enter Keyword or ID”, enter BSEE-2013-0011 then click search. Follow the instructions to submit public comments and view supporting and related materials available for this rulemaking. BOEM and BSEE may post all submitted comments in their entirety. • Mail or hand-carry comments to the Department of the Interior (DOI); Bureau of Safety and Environmental Enforcement; Attention: Regulations and Standards Branch; 45600 Woodland Road, Sterling, Virginia 20166. Please reference “Oil and Gas and Sulphur Operations on the Outer Continental Shelf—Requirements for Exploratory Drilling on the Arctic Outer Continental Shelf, 1082-AA00” in your comments and include your name and return address. Please note that this address for BSEE is new; however, any comments already submitted to BSEE's former address (381 Elden Street, Herndon, Virginia 20181) do not need to be resubmitted to the new address. • Public Availability of Comments—Before including your address, phone number, email address, or other personal identifying information in your comment, you should be aware that your entire comment—including your personal identifying information—may be made publicly available at any time. While you can ask us in your comment to withhold your personal identifying information from public review, we cannot guarantee that we will be able to do so.
      30 CFR Parts 250 and 254