30 CFR 250.911 - If my platform is subject to the Platform Verification Program, what must I do?

§ 250.911 If my platform is subject to the Platform Verification Program, what must I do?

If your platform, conversion, or major modification or repair meets the criteria in § 250.910, you must:

(a) Design, fabricate, install, use, maintain and inspect your platform, conversion, or major modification or repair to your platform according to the requirements of this subpart, and the applicable documents listed in § 250.901(a) of this subpart;

(b) Comply with all the requirements of the Platform Approval Program found in §§ 250.904 through 250.908 of this subpart.

(c) Submit for the Regional Supervisor's approval three copies each of the design verification, fabrication verification, and installation verification plans required by § 250.912;

(d) Submit a complete schedule of all phases of design, fabrication, and installation for the Regional Supervisor's approval. You must include a project management timeline, Gantt Chart, that depicts when interim and final reports required by §§ 250.916, 250.917, and 250.918 will be submitted to the Regional Supervisor for each phase. On the timeline, you must break-out the specific scopes of work that inherently stand alone (e.g., deck, mooring systems, tendon systems, riser systems, turret systems).

(e) Include your nomination of a Certified Verification Agent (CVA) as a part of each verification plan required by § 250.912;

(f) Follow the additional requirements in §§ 250.913 through 250.918;

(g) Obtain approval for modifications to approved plans and for major deviations from approved installation procedures from the Regional Supervisor; and

(h) Comply with applicable USCG regulations for floating OCS facilities.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS

Title 30 published on 20-Dec-2017 04:15

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR Part 250 after this date.

  • 2017-12-29; vol. 82 # 249 - Friday, December 29, 2017
    1. 82 FR 61703 - Oil and Gas and Sulphur Operations on the Outer Continental Shelf—Oil and Gas Production Safety Systems—Revisions
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Proposed rule.
      Submit comments by January 29, 2018. BSEE may not fully consider comments received after this date. You may submit comments to the Office of Management and Budget (OMB) on the information collection burden in this proposed rule by January 29, 2018. The deadline for comments on the information collection burden does not affect the deadline for the public to comment to BSEE on the proposed regulations.
      30 CFR Part 250