For a renewable energy system or energy efficiency improvement project to be eligible to receive a RES or EEI grant under this subpart, the proposed project must meet each of the criteria, as applicable, in paragraphs (a) through (j), as applicable, of this section, and is subject to the limitations specified in paragraph (k) of this section.
(a) The project must be for the purchase of a renewable energy system or to make energy efficiency improvements. Energy efficiency improvements to existing renewable energy systems are eligible energy efficiency improvement projects.
(b) The project must be for a pre-commercial or commercially available, and replicable technology.
(c) The project must have technical merit, as determined using the procedures specified in § 4280.117(b).
(d) The facility for which the project is being proposed must be located in a rural area, as defined in § 4280.103, in a State if the type of applicant is a rural small business, or in a rural or non-rural area in a State if the type of applicant is an agricultural producer. If the agricultural producer's facility is in a non-rural area, then the application can only be for renewable energy systems or energy efficiency improvements on integral components of or that are directly related to the facility, such as vertically integrated operations, and are part of and co-located with the agriculture production operation.
(e) The applicant must have a place of business in a State.
(f) The applicant must be the owner of the project and control the revenues and expenses of the project, including operation and maintenance. A third-party under contract to the owner may be used to control revenues and expenses and manage the operation and/or maintenance of the project.
(g) Sites must be controlled by the agricultural producer or rural small business for the financing term of any associated Federal loans or loan guarantees.
(h) Satisfactory sources of revenue in an amount sufficient to provide for the operation, management, maintenance, and debt service of the project must be available for the life of the project.
(i) For the purposes of this subpart, only hydropower projects with a rated power of 30 megawatts or less are eligible. The Agency refers to these hydropower sources as “small hydropower,” which includes hydropower projects commonly referred to as “micro-hydropower” and “mini-hydropower.”
(j) The project has demonstrated technical feasibility.
(k) No renewable energy system or energy efficiency improvement, or portion thereof, can be used for any residential purpose, including any residential portion of a farm, ranch, agricultural facility, or rural small business. However, an applicant may apply for funding for the installation of a second meter or provide certification in the application that any excess power generated by the renewable energy system will be sold to the grid and will not be used by the applicant for residential purposes.
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 4280.113 Project eligibility.

For a project to be eligible to receive a RES or EEI grant under this subpart, the proposed project must meet each of the requirements specified in paragraphs (a) through (f) of this section.

(a) Be for:

(1) The purchase of a new RES;

(2) The purchase of a Refurbished RES;

(3) The Retrofitting of an existing RES; or

(4) Making EEI that will use less energy on an annual basis than the original building and/or equipment that it will improve or replace as demonstrated in an Energy Assessment or Energy Audit as applicable.

(i) Types of improvements. Eligible EEI include, but are not limited to:

(A) Efficiency improvements to existing RES and

(B) Construction of a new energy efficient building only when the building is used for the same purpose as the existing building, and, based on an Energy Assessment or Energy Audit, as applicable, it will be more cost effective to construct a new building and will use less energy on annual basis than improving the existing building.

(ii) Subsequent Energy Efficiency Improvements. A proposed EEI that replaces or duplicates an EEI previously funded under this subpart may or may not be eligible for funding.

(A) If the proposed EEI would replace or duplicate the same EEI that had previously received funds under this subpart prior to the end of the useful life, as specified in the Grant Agreement, of that same EEI, then the proposed improvement, even if it is more energy efficient than the previously funded improvement, is ineligible. Example: An Applicant received a REAP grant to replace an exhaust fan (exhaust fan A) in a barn with a more energy efficient exhaust fan (exhaust fan B) with an expected useful life of 15 years, as specified in the Grant Agreement. If the Applicant decides to replace exhaust fan B after 8 years (i.e., before it has reached the end of its useful life as specified it the Grant Agreement), an application for exhaust fan C to replace exhaust fan B would be ineligible for funding under this subpart even if exhaust fan C is more energy efficient than exhaust fan B.

(B) If the proposed EEI would replace or duplicate the same EEI that had previously received funds under this subpart at or after the end of the useful life, as specified in the Grant Agreement, of that same EEI, then the proposed improvement is eligible for funding under this subpart provided it is more energy efficient than the previously funded improvement. If the proposed EEI is not more energy efficient than the previously funded improvement, then it is not eligible for funding under this subpart.

(b) Be for a Commercially Available technology;

(c) Have technical merit, as determined using the procedures specified in § 4280.116; and

(d) Be located in a Rural Area in a State if the type of Applicant is a Rural Small Business, or in a Rural or non-Rural Area in a State if the type of Applicant is an Agricultural Producer. If the Agricultural Producer's operation is in a non-Rural Area, then the application can only be for RES or EEI on components that are directly related to and their use and purpose is limited to the agricultural production operation, such as vertically integrated operations, and are part of and co-located with the agricultural production operation.

(e) For an RES project in which a residence is closely associated with and shares an energy metering device with a Rural Small Business, where the residence is located at the place of business, or agricultural operation, the application is eligible if the applicant can document that one of the options specified in paragraphs (e)(1) through (3) of this section is met:

(1) Installation of a second meter (or similar device) that results in all of the energy generated by the RES being used for non-residential energy usage;

(2) Certification is provided in the application that any excess power generated by the RES will be sold to the grid and will not be used by the Applicant for residential purposes; or

(3) Demonstration that 51 percent or greater of the energy to be generated will benefit the Rural Small Business or agricultural operation. The Applicant must provide documentation that includes, but is not limited to, the following:

(i) A Renewable Energy Site Assessment; or

(ii) The amount of energy that is used by the residence and the amount that is used by the Rural Small Business or agricultural operation. Provide documentation, calculations, etc. to support the breakout of energy amounts. The Agency may request additional data to determine residential versus business operation usage; and

(iii) The actual percentage of energy determined to benefit the Rural Small Business or agricultural operation will be the basis to determine eligible project costs.

(f) The Applicant is cautioned against taking any actions or incurring any obligations prior to the Agency completing the environmental review that would either limit the range of alternatives to be considered or that would have an adverse effect on the environment, such as the initiation of construction. If the Applicant takes any such actions or incurs any such obligations, it could result in project ineligibility.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 7 published on 2015-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 7 CFR Part 4280 after this date.

  • 2015-03-26; vol. 80 # 58 - Thursday, March 26, 2015
    1. 80 FR 15885 - Rural Development Regulations—Update to FmHA References and to Census References
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, Rural Business-Cooperative Service, Rural Utilities Service, Rural Housing Service, Farm Service Agency
      Correction; direct final rule.
      This document is effective April 27, 2015.
      7 CFR Parts 1709, 1714, 1735, 1737, 1738, 1739, 1740, 1774, 1775, 1776, 1777, 1778, 1779, 1780, 1781, and 1783