3 AAC 52.460 - Quality of service
(a) A utility shall, except in the case of
conditions caused by the utility's customers, maintain a steady-state standard
frequency of 60 Hertz within the following tolerances:
(1) wherever 2,000 or more customers of one
or more utilities are served by an isolated or interconnected transmission or
distribution system, frequency must be held within plus or minus two percent of
standard frequency; cumulative error registered by an electric clock over a
24-hour period may not exceed 90 seconds; and
(2) for other service areas, frequency must
be held within plus or minus two cycles of standard frequency.
(b) A utility shall provide
various standard voltages as stated in its tariff, and shall comply with the
voltage standard set out in section C84.1-1982 of the American National
Standards Institute.
(c) At
intervals not to exceed one year a utility shall calculate customer primary
voltage to determine the voltage profile of its primary distribution feeders
over a 12-hour period during the season of peak demand and including the hours
of maximum load. Records supporting the voltage profiles must include the
location and parameters of any test and must be available for inspection by the
commission for a period of two years after the date of the test.
(d) A utility shall establish planning and
preventive maintenance procedures designed to provide a reasonable level of
uninterrupted service and, if interruptions occur, to speed the restoration of
service.
(e) If scheduled outages
are necessary, a utility shall make a good faith effort to do the work at a
time that will cause minimal inconvenience to customers, and to notify
customers in advance of the interruption. A utility shall develop and maintain
a plan for notifying customers of a scheduled outage that is appropriate to the
utility's available personnel levels and geographic location. The utility's
plan must include public notification when five percent or more of a utility's
customers in its certificated service area or all customers within a
reliability reporting area are affected.
(f) A utility shall develop and maintain an
outage contingency plan, including a public information plan, which is
appropriate to the utility's location and size.
(g) A utility shall maintain detailed records
of planned and unplanned outages and of interruptions of service. These records
must include the cause, whether planned or unplanned, duration, location of the
outage, and the approximate number of customers affected. These records must be
available to the public. For purposes of this subsection, a momentary
fluctuation does not constitute an interruption of service.
Notes
Copies of section C84.1-1982 of the American National Standards Institute, mentioned in 3 AAC 52.460(b), may be obtained at the offices of the Regulatory Commission of Alaska as specified in 3 AAC 48.010(a).
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.291
AS 42.05.691
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.