3 AAC 52.710 - Certificate of public convenience and necessity
(a) A water or
wastewater utility must obtain a certificate of public convenience and
necessity before it provides service to 15 or more service connections unless
it is exempt from regulation under
3
AAC 52.700 or is qualified for provisional
certification under
3
AAC 52.720. A utility that is provisionally
certificated under
3
AAC 52.720 -
3
AAC 52.724 must obtain a certificate of public
convenience and necessity if it no longer meets the criteria in
3
AAC 52.720 for provisional certification. A utility
that is exempt under
3
AAC 52.700 or qualified for provisional certification
under 3 AAC 52.720 may apply for a
certificate of public convenience and necessity.
(b) Except as provided in (c) of this
section, an applicant for a certificate of public convenience and necessity
must provide the following information on a form prescribed by the commission:
(1) the applicant's legal name and the name
under which it proposes to do business;
(2) the address of the applicant's principal
national place of business, and, if different, its place of business in this
state;
(3) the name, title, and
telephone number of the individual who is available to provide the commission
with information about the application;
(4) the applicant's type of business
structure, including
(A) proof of
incorporation, registration, or certification, if applicable; and
(B) the name and address of the applicant's
registered agent, if applicable;
(5) the names, titles, responsibilities, and
qualifications of key management the applicant employs or will employ,
including the individuals responsible for the oversight of its financial and
technical staff;
(6) a statement
explaining why the public convenience and necessity requires the utility
service the applicant will provide;
(7) the name of any other utility providing
similar service in, or within one mile of, the area the applicant proposes to
serve;
(8) the number and type of
customers the applicant expects to serve, by geographic location;
(9) for an existing system, a copy of the
approval from the Department of Environmental Conservation to operate a
domestic wastewater system under
18 AAC 72.240 or to operate a
public water system under
18 AAC 80.210, as applicable; if
the applicant has not yet obtained operating approval, the applicant must file
a schedule agreed to by the Department of Environmental Conservation to
complete that department's technical requirements for all utility plant that is
under construction;
(10) for a
water utility, a description of each source of water for the proposed service
area, including
(A) the quantity
available;
(B) pumping capacity for
each source;
(C) reservoir
capacity;
(D) the available reserve
capacity, in hours, in case of power outages or well failure; and
(E) information regarding the treatment
necessary to bring the water into compliance with 18 AAC 80;
(11) for a wastewater utility,
(A) a description of the collection system
and treatment facilities;
(B)
information regarding the treatment necessary to bring the discharge into
compliance with 18 AAC 70 and 18 AAC 72, and the method of disposal of treated
effluent for the proposed service area; and
(C) information on the receiving environment
into which the effluent will be discharged;
(12) documentation that the applicant
complies with the Department of Environmental Conservation's operator
certification requirements at
18 AAC 74.010; if the applicant is
not in compliance with the operator certification requirements, the applicant
must file a schedule to come into compliance with those requirements;
(13) a statement confirming that a water
meter is installed, calibrated, and working at the entrance to the distribution
system;
(14) a written description
and a map of the utility's proposed service area;
(15) a tariff of rates and services that
complies with
3
AAC 48.320 -
3
AAC 48.390 if the utility will be subject to economic
regulations within the meaning of
3
AAC 48.820, or that complies with
3
AAC 52.730 -
3
AAC 52.740 if the utility will not be subject to
economic regulations within the meaning of
3
AAC 48.820;
(16) pro forma financial schedules showing
the calculation of the rate base for the utility using the appropriate uniform
standard of accounts applicable under
3
AAC 48.277 to the utility;
(17) an income statement and balance sheet
for the most recent fiscal year for existing systems; an actual income
statement and balance sheet from the owner of the utility may be substituted
for a new water or wastewater utility that has not begun providing service or
that has not completed a full fiscal year of service;
(18) information on the sources of financing
for the utility, including grants and loans;
(19) a verification signed by the person
authorized to sign on behalf of the applicant that all of the information
provided in the application is true, accurate, and complete;
(20) additional filings as required by the
commission to explain or supplement the information filed under this
subsection.
(c) An
applicant that has previously obtained a finding of public convenience and
necessity under
3
AAC 52.715 is not required to re-submit information
required under (b) of this section unless the information is not currently
correct.
(d) The commission will
determine if an application for a certificate of public convenience and
necessity is complete within 15 business days after the receipt of an
application. An incomplete application will be handled as provided in
3
AAC 48.650.
(e) The commission will give notice of an
application for a certificate of public convenience and necessity as provided
in 3 AAC
48.645(a).
(f) If the commission denies an application,
the utility may request a hearing as provided in
AS
42.05.171.
Notes
As of Register 178 (July 2006), the regulations attorney made technical revisions under AS 44.62.125(b)(6), to 3 AAC 52.710(e) and (f).
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.221
AS 42.05.241
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.