Ariz. Admin. Code § R14-2-2617 - Level 1 Super Fast Track
A. A
Customer interconnecting an inverter-based Generating Facility with a Maximum
Capacity of 20 kW or less, which only uses Certified Equipment, shall apply for
Interconnection under the Level 1 Super Fast Track Application
process.
B. To qualify for Level 1
Super Fast Track, the Generating Facility shall comply with R14-2-2615(A), (E), and (F).
C. The Level 1 Super Fast
Track shall proceed as follows:
1. Within 14
calendar days following provision of notice under R14-2-2614(D)(1), the Utility
shall review the Application and notify the Applicant of one of the following
determinations:
a. The Generating Facility
design satisfies R14-2-2615(A), (E), and (F) and meets all Interconnection
requirements and the Application is therefore deemed complete and approved for
Interconnection; or
b. The
Generating Facility design does not satisfy one or more of the requirements
listed in R14-2-2615(A), (E), or (F) or does not meet one or more of the
Utility's Interconnection requirements, which shall be specified, and the
Application is therefore deemed incomplete and not approved for
Interconnection.
2. If
the Utility's determination falls under subsection (C)(1)(b), the Applicant
shall notify the Utility within 30 calendar days whether it wishes to proceed
with the Interconnection.
a. Except as
provided in subsection (D), if the Applicant does not provide notice within 30
calendar days that it wishes to proceed with the Interconnection, the
Application may be considered withdrawn.
b. If the Applicant wishes to proceed with
the Interconnection, the Applicant shall submit to the Utility, within 30
calendar days, any Utility-specified additional information or modifications to
the Generating Facility, along with one of the following:
i. A request that the Utility continue to
process the Application under this section; or
ii. A request that the Utility process the
Application in accordance with R14-2-2620.
3. Once an Application is approved, the
Generating Facility shall be subject to R14-2-2621.
D. An Applicant may, within 30 calendar days
after receiving notice under subsection (C)(1)(b), submit a request for an
extension of the 30-day period allowed for submissions under subsection
(C)(2)(b).
E. After receiving a
submission under subsection (C)(2)(b), a Utility shall again follow the process
of subsection (C).
F. A Utility may
not charge a fee for an additional review under subsection (C), unless a tariff
containing such a fee is approved for the Utility by the Commission.
G. A Customer shall be responsible for any
costs of Utility facilities and equipment modifications necessary to
accommodate the Customer's Interconnection.
H. If the Generating Facility's operating
characteristics can be modified such that improvements to the Distribution
System are reduced or not required, and both the Utility and Customer agree on
the operating characteristics, the Customer shall have the opportunity to
modify the Generating Facility's operating characteristics to reduce facility
costs.