Ariz. Admin. Code § R14-2-2627 - Electric Cooperatives
A. Upon
Commission approval of an Electric Cooperative's Interconnection Manual, its
provisions shall substitute for the timeline requirements set forth in
R14-2-2614 and R14-2-2616 through R14-2-2623 for the Electric Cooperative and
its Customers.
B. Each Electric
Cooperative shall employ best reasonable efforts to comply with the deadlines
set forth in the applicable provisions of this Article or, if unable to meet
those deadlines, shall process all Applications and conduct all inspections and
tests in the shortest time practical.