Ariz. Admin. Code § R18-9-E318 - 4.18 General Permit: Constructed Wetland, Less Than 3000 Gallons Per Day Design Flow
A. A 4.18 General
Permit allows for the use of a constructed wetland receiving wastewater treated
to a level equal to or better than that specified in
R18-9-E302(B) .
1. Definition. "Constructed wetland" means a
treatment technology characterized by a lined excavation, filled with a medium
for growing plants and planted with marsh vegetation. The treated wastewater
flows horizontally through the medium in contact with the aquatic plants.
a. As the wastewater flows through the
wetland system, additional treatment is provided by filtering, settling,
volatilization, and evapotranspiration.
b. The wetland system allows microorganisms
to break down organic material and plants to take up nutrients and other
pollutants.
c. The wastewater
treated by a wetland system is discharged to a subsurface soil disposal
system.
2. An applicant
may use a constructed wetland if further wastewater treatment is needed before
disposal.
B. Performance.
An applicant shall ensure that a constructed wetland is designed so that it
produces treated wastewater that meets the following criteria:
1. TSS of 20 milligrams per liter, 30-day
arithmetic mean;
2.
BOD5 of 20 milligrams per liter, 30-day arithmetic
mean;
3. Total nitrogen (as
nitrogen) of 45 milligrams per liter, five-month arithmetic mean; and
4. Total coliform level of 100,000
(Log10 5) colony forming units per 100 milliliters, 95th
percentile.
C. Notice of
Intent to Discharge. The applicant shall comply with the Notice of Intent to
Discharge requirements specified in
R18-9-A301(B)
and R18-9-A309(B).
D. Design, installation, operation, and
maintenance requirements. The permittee shall comply with the applicable
design, installation, operation, and maintenance requirements in
R18-9-A312,
R18-9-A313(A),
and R18-9-A313(B).
E. Reference design.
1. An applicant may use a constructed wetland
that achieves the performance requirements in subsection (B) by following a
reference design on file with the Department.
2. The applicant shall file a form provided
by the Department for supplemental information about the proposed constructed
wetland with the applicant's submittal of the Notice of Intent to
Discharge.