Fla. Admin. Code Ann. R. 60D-5.008 - Qualifications-Based Selection; Contractor Selection and Negotiation Procedures for Projects Within Level Four and Level Five Contracts
(1) The Secretary of the Department may waive
the requirements of Rule
60D-5.0073, F.A.C., and permit
negotiation of construction contracts in accordance with Rules
60D-5.0082 and
60D-5.0091, F.A.C., in cases
determined by him to be in the best interest of the State.
(2) In making a determination of best
interest of the State, the Secretary of the Department may consider such
factors as:
(a) Is the need for the facility
significant enough to require a substantial reduction of normal delivery time,
requiring overlap of design and construction development phases?
(b) Is the size of the project large,
requiring major emphasis on the qualification of the contractor because of the
highly specialized requirements for scheduling, value engineering, and
construction management?
(c) Is the
complexity of the project significant, requiring a contractor with specific
expertise to be applied to the design process with continuity through the
construction phase?
(d) Is the
project construction funding spread out over more than one year thereby making
it advantageous to retain a contractor through a construction
management/negotiated fee-guaranteed maximum price form of agreement?
(e) Is the project an alteration of an
occupied facility which requires working around or relocating occupants while
keeping the facility fully operational?
(f) Is the project a repair or renovation
where the conditions requiring correction cannot be fully determined and
specified without contractor involvement in the removal and examination process
as an integral part of design (e.g., concealed damages, removal of asbestos,
transformers containing PCB's, etc.)?
(g) Is the project one which is predominantly
historic preservation/restoration requiring a specifically qualified
contractor's involvement in the design process with continuity of construction
management through both the design and construction phases?
(h) Is the Agency able and qualified to
perform the contractor selection and contract negotiation in accordance with
Rules 60D-5.0082 and
60D-5.0091, F.A.C., as
determined by the Division?
(i) Are
the construction services required to perform the work on the project available
only from one contractor, for a "single source contract"?
(3) In requesting in writing the authority to
negotiate from the Secretary, the Agency shall respond to the applicable
factors in subsection
60D-5.008(2),
F.A.C., in sufficient detail to justify the authority and will certify to the
Secretary that such factors exist, and that negotiation of the construction
contract will accommodate reduction in delivery time, size and complexity,
special expertise, funding cycles or any of the factors under
consideration.
Notes
Rulemaking Authority 255.29, 255.30 FS. Law Implemented 255.29, 255.30 FS.
New 5-26-76, Amended 1-2-78, 7-14-81, 7-7-83, Formerly 13D-11.08, Amended 1-25-89, 11-5-91, Formerly 13D-11.008, Amended 12-3-14.