Nev. Admin. Code § 445A.4155 - Conditions pursuant to which modification to design of facility with existing permit does not require new public notice; extension of term of existing permit disallowed
1. A modification to the engineering design of a facility for which a permit has been granted by the Department does not require a new public notice if:
2. A modification to the engineering design described in subsection 1 may not extend the term of the permit.
3. Examples of modifications to the engineering design of a facility which do not constitute a major or minor modification and do not require a new public notice pursuant to subsection 1 include, without limitation:
(a) A change to process fluid containment;
(b) A proposal to construct or modify materially a beneficiation or non-beneficiation process component;
(c) A material modification that significantly deviates from a previously approved design during construction;
(d) A change to a previously approved design that requires a revised analysis of structural stability in an engineering design report pursuant to NAC 445A.397;
(e) A proposed increase of process solution flow in excess of a maximum design rate previously authorized in the permit;
(f) A proposed change requiring the permit to be revised, which may include a change to monitoring requirements, monitoring frequency, the schedule of compliance or permit limitations;
(g) A change to the operating plans if the change alters the potential to degrade the waters of the State; and
(h) Proposed drilling or reprocessing of closed process components.