Utah Admin. Code R746-700 - Complete Filings for General Rate Case and Major Plant Addition Applications
- § R746-700-1 - General Provisions Applicable to All 7XX Series Rules
- § R746-700-10 - Test Period Information to Be Included With a General Rate Case Application
- § R746-700-20 - Information For a General Rate Case Application for an Electrical Corporation or a Gas Corporation
- § R746-700-21 - Cost of Service and Rate Design Information for a General Rate Case Application for an Electrical Corporation or a Gas Corporation
- § R746-700-22 - Additional Information for a General Rate Case Application Using a Forecasted Test Period Filed by an Electrical Corporation or a Gas Corporation
- § R746-700-23 - Additional Power Costs Information for a Forecasted Test Period to Be Filed by an Electrical Corporation
- § R746-700-30 - Information for an Alternative Cost Recovery for a Major Plant Addition Application Filed by an Electrical Corporation or a Gas Corporation
- § R746-700-40 - Information for a General Rate Case Application for a Telecommunications Corporation
- § R746-700-41 - Cost of Service and Rate Design Information for a General Rate Case Application for a Telecommunications Corporation
- § R746-700-50 - Information for a General Rate Case Application for a Water Corporation
- § R746-700-51 - Cost of Service and Rate Design Information for a General Rate Case Application for a Water Corporation
Notes
54-7-12(1)(b)(ii); 54-7-13.4(1)(a)(ii)
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.