010-2 Wyo. Code R. §§ 2-26 - Timely Correction for Critical Item Violation
(a) Except as
specified in Chapter 2, Section
26(b), a license holder
shall at the time of inspection correct a critical violation of this Rule or
implement corrective actions for a HACCP plan provision that is not in
compliance with its critical limit.
(b) Considering the nature of the potential
hazard involved and the complexity of the corrective action needed, the
regulatory authority may agree to or specify a longer time frame, not to exceed
ten (10) calendar days after the inspection, for the license holder to correct
critical violations of this Rule or HACCP plan deviations.
(i) If a determination by the inspector that
the corrective action cannot be completed within 10 (ten) days, the inspector
may request an extension be granted which must be approved in writing by a
supervisor.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.