The Director of the Foundation shall strengthen oversight and accountability over the full life-cycle of each major multi-user research facility project, including planning, development, procurement, construction, operations, and support, and shut-down of the facility, in order to maximize research investment.
Subject to subsection (c)(1), the Director of the Foundation shall require that any pre-award analysis of a major multi-user research facility project includes the development and consideration of the full life-cycle cost (as defined in section 2 of the National Science Foundation Authorization Act of 1998 (42 U.S.C. 1862k note)) in accordance with section 1862n–4 of this title.
Based on the pre-award analysis described in paragraph (1), the Director of the Foundation shall include projected operational costs within the Foundation’s out-years as part of the President’s annual budget submission to Congress under section 1105 of title 31.
The Director of the Foundation shall require an independent cost analysis of the operational proposal for each major multi-user research facility project.
The Director of the Foundation shall strengthen internal controls to improve oversight of contingency on a major multi-user research facility project.
The Director of the Foundation shall establish guidelines for awardees regarding inappropriate expenditures associated with all fee types used in cooperative agreements, including for alcoholic beverages, lobbying, meals or entertainment for non-business purposes, non-business travel, and any other purpose the Director determines is inappropriate.
The term “appropriate committees of Congress” means the Committee on Commerce, Science, and Transportation and the Committee on Appropriations of the Senate and the Committee on Science, Space, and Technology and the Committee on Appropriations of the House of Representatives.
The term “major multi-user research facility project” means a science and engineering facility project that exceeds $100,000,000 in total construction, acquisition, or upgrade costs to the Foundation.