§ 222.174 What prohibitions apply to these funds?
Grant funds under this program may not be used to supplant or replace other available non-Federal construction money. These grant funds may be used for emergency or modernization activities only to the extent that they supplement the amount of construction funds that would, in the absence of these grant funds, be available to a grantee from non-Federal funds for these purposes.
Example 1. “Supplanting.”
An LEA signs a contract for a $300,000 roof replacement and plans to use its capital expenditure fund to pay for the renovation. Since the LEA already has non-Federal funds available for the roof project, it may not now use a grant from this program to pay for the project or replace its own funds in order to conserve its capital fund.
Example 2. “Non-supplanting.”
The LEA from the example of supplanting that has the $300,000 roof commitment has also received a $400,000 estimate for the replacement of its facility's heating, ventilation, and air conditioning (HVAC) system. The LEA has not made any commitments for the HVAC system because it has no remaining funds available to pay for that work. Since other funds are not available, it would not be supplanting if the LEA received an emergency grant under this program to pay for the HVAC system.
(Authority: 20 U.S.C. 7707(b))
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 222.174 What prohibitions apply to these funds?

Grant funds under this program may not be used to supplant or replace other available non-Federal construction money. These grant funds may be used for emergency or modernization activities only to the extent that they supplement the amount of construction funds that would, in the absence of these grant funds, be available to a grantee from non-Federal funds for these purposes.

Example 1. “Supplanting.”
An LEA signs a contract for a $300,000 roof replacement and plans to use its capital expenditure fund to pay for the renovation. Since the LEA already has non-Federal funds available for the roof project, it may not now use a grant from this program to pay for the project or replace its own funds in order to conserve its capital fund.
Example 2. “Non-supplanting.”
The LEA from the example of supplanting that has the $300,000 roof commitment has also received a $400,000 estimate for the replacement of its facility's heating, ventilation, and air conditioning (HVAC) system. The LEA has not made any commitments for the HVAC system because it has no remaining funds available to pay for that work. Since other funds are not available, it would not be supplanting if the LEA received an emergency grant under this program to pay for the HVAC system.
(Authority: 20 U.S.C. 7707(b))

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 20 - EDUCATION
U.S. Code: Title 29 - LABOR
U.S. Code: Title 37 - PAY AND ALLOWANCES OF THE UNIFORMED SERVICES
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE
Statutes at Large
Public Laws

92-318

Title 34 published on 2015-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 34 CFR Part 222 after this date.

  • 2015-11-02; vol. 80 # 211 - Monday, November 2, 2015
    1. 80 FR 67261 - Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards; Direct Grant Programs
      GPO FDSys XML | Text
      DEPARTMENT OF EDUCATION
      Final regulations.
      These regulations are effective December 2, 2015.
      2 CFR Part 3474