Utah Admin. Code R746-313-6 - Inquiries About Electric Service Reliability
(1) A customer may request a report from its
electric company about the reliability of the electric service provided to the
customer's own meter which the electric company must provide at no cost within
20 business days of the request. If a customer requests one or more additional
reliability reports for the same meter within one year of the date of the first
request, the electric company may charge the customer the cost of preparing the
reports.
(2) For an electric
company whose governing authority is the commission, the report to the customer
must include:
(a) The name of the
customer;
(b) The date of the
request;
(c) The address where the
meter is installed;
(d) The meter
identification number;
(e) The
general identification of the equipment serving the customer; and
(f) A chronological listing of interruptions
to the customer including any associated interruption data required by
Subsection R746-313-5(2)
covering at least the 36 months preceding the date of the request, if
available. If 36 months of data are not available, the chronological listing
must include any available data.
(3) For an electric company whose governing
authority is not the commission, the report to the customer must include:
(a) The name of the customer;
(b) The date of the request;
(c) The address where the meter is
installed;
(d) The meter
identification number;
(e) The
general identification of the equipment serving the customer; and
(f) A chronological listing of interruptions
on the feeder serving the customer's meter including any interruption data
required by Subsection
R746-313-5(2)
covering at least the 12 months preceding the date of the request. If 12 months
of data are not available, the chronological listing must include any available
data.
(4) Other than
those inquiries named in Subsection
R746-313-6(1),
each electric company must have a written policy for consistent treatment of
each inquiry pertaining to electric reliability. At the least, the electric
company must provide to the inquiring person, by electronic means, the electric
company's most recently filed report on electric service reliability required
by Section R746-313-7.